V

SHAHPURKANDI  EXTENSION (55.5 MW)

1)

Location

This project is to be executed on UBDC  Main Canal.

2)

Main Features:

Power will be generatyed from water used for Irrigation purpose.

3)

No. of Power Houses.

3

4)

No. of Units:

6 (2 each at above Power Houses)

2x10.5+2x10.5+2x6.75= 55.5MW

5)

Total generating capacity

Punjab Share = 55.5 MW

6)

Design Head:

54.6 Mtr.

7)

Design Discharge:

185 cumecs with 10% overloading.

8)

Type of Development

Run  through canal

9)

Commissioning:

End 2015-16

10)

Cost of Project:

Rs. 498.83 Crore at 2000  price level

11)

Total Energy Contribution Annually

 

12)

Cost per unit:

Rs. 3.56  at 2000 price level

13)

  Present Status

This project is proposed to be developed by re-modeling the existing UBDC canal from Madhopur Head Works up to RD 65000 ft. It involves construction of 3 No. PHs. The capacity of the channel after remodeling shall be 13500 cusecs and the total length of the channel will be about 20 KMs. The cost of the project is approximately Rs.500 Cr. at Nov.2000 price level and the annual generation shall be about 192 MU. The project will be developed on BOOT basis. Chief Engineer/SPKD has been requested to revise the DPR so as to arrive at the current cost of the Project.

Note:-

The capacity of the SKPP  is yet to be decided as 55.5 MW or 81 MW as the design discharge is yet to be finalised due to difference of opinion. The detailed calculations in this regard are being made for proper evaluation .



About Us | Feedback | Admin Login
Developed and Maintained by Phoenix IT Solutions Ltd.
©2010 PSPCL & PSTCL -All Rights Reserved