|
C.C. No. 67/2006
Memo
No. 87252/88052/SSM-460
Dated. 21/12/06
Sub: T&D Loss Reduction and Improvement in Consumer service Instructions
thereof.
With a view to take concrete steps to
achieve the desired target for reduction in T&D losses, instructions were
issued vide CC No.37/06 dated 18.7.06. However,
in view of the difficulties being experienced by the field officers in
implementing these instructions in letter and spirit, no. of clarifications
are being sought by them. Keeping
in view these practical difficulties in implementing HVDS Scheme as such &
based on the feedback from the field officers, the matter has been reviewed
and it has been decided as under:-
(i) In case of shifting of AP
tubewell connection, shifting may be allowed on LT if it is technically
feasible to release the connection at the new site on LT i.e. if the feeding
transformer at the new site can take up the load. However, if for allowing tubewell connection at the new site,
augmentation of transformer is involved then the connection at the new site
shall be released only under HVDS as per the instructions issued vide CC No.
37/06 and the cost of transformer in addition to other applicable charges
shall also be borne by the consumer. However,
in case where notice had already been issued to the consumer on or before 30.9.2006 for deposit of charges for
shifting of tubewell connection, then shifting shall be carried out as per
notice served to the consumer.
(ii) For DS/NRS loads above 10 KW and upto 20 KW and SP connections:-
(a) Connection shall be released on
LT provided the length of LT line including the existing LT line from H-pole
near the transformer does not exceed
250 metres
in any case and no augmentation of the existing distribution transformer is
required. However, if the existing
transformer is of less than 200 KVA capacity then it can be augmented upto 200
KVA for release of connection on LT.
(b) In case where augmentation of
transformer beyond 200 KVA is required, the connection shall be released only
by providing new transformer of suitable capacity & LT line of the
de-loaded transformer further to new transformer shall be shifted to the new
transformer.
(c) In case where the new connection
is required to be released on HVDS but it is not possible to release the
connection on HVDS due to locational/practical constraint, such connection
shall be allowed to be released on LT with the approval of Addl.SE/Sr.Xen who
will record reasons for allowing such relaxation.
(iii) For DS/NRS consumers with loads above 20 KW:-
(d) In case where the existing
transformer can take the load to be released with maximum length of LT from
the transformer limited to
250 metres
, the same be released from the existing transformer.
(e) If augmentation of existing
transformer is required to release the load on LT, it should be released by
providing additional transformer of required capacity at the load center and
LT around the proposed transformer will be shifted to this new transformer
ensuring maximum improvement in the LD system.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C. No.66/2006
Memo No.84797/85597/SSM-414/TW/L-124
Dated.
19/12/06
Subject:- Release of new tubewell connections under Chairman Priority quota –
clarification thereof.
Field officers have
sought clarification as to whether the connections under Chairman's Priority
quota are to be released by providing the distribution transformer at Board's
cost or the prospective consumers may be asked to provide their own
transformer.
In
this context ,it is clarified that as per instructions already issued vide CC
No. 47/05 dated 20.7.05 followed by CC No. 68/05 dated 1.12.05 and CC No.
13/06 dated 17.3.06 ,all new AP tubewell connections under Chairman's
discretionary quota were to be
released on LT through Board's own transformer . As per CC 37/06 dated
18.7.06,all new AP tubewell connections are to be released under HVDS only w.e.f 1.10.06 onwards by providing individual small
distribution transformer for each connection on single pole structure at
Board's cost subject to recovery of service connection charges as per existing
instructions.
In
view of the position explained above, it is clarified that new AP tubewell
connections under Chairman's discretionary quota are also to be released by
providing individual small distribution transformer for each connection on
single pole structure at Board's cost .
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.65/2006
Memo
No. 81953/82753/SSM-416
Dated.
11/12/06
Subject:- Providing Urban Pattern Supply to Dalit Basties ,Be-Chirag Villages & Deras/Dhanies having cluster of 5 or more houses.
The precondition of
minimum 20 houses for providing Urban Pattern Supply to the village Dhanies /Deras at the cost of Board by laying single phase 11
KV system was relaxed to 15 houses vide CC No.20/2004 dated 19.4.2004.
On the persistent demand of
farmers/residents presently residing in Deras/Dhanies, Dalit Basties, Be-chirag
villages etc. forming a cluster of 5 or more houses and located at a distance
of more than 500 mtrs. from the
village phirni, for urban pattern supply The matter has been considered & it has been decided as under :-
(i) Urban Pattern Supply, shall be provided at the Board's cost to
the farmers/residents presently residing in Deras/Dhanies ,Dalit Basties, Be-Chirag Villages forming a cluster of 5 or more houses situated
adjoining to each other and spread over in a stretch of maximum of
300 meters
from one end to the other end and located at a distance more than
500 meters
from the village Phirni without any limit by providing:-
(a) Single phase 11 KV line tapped from the nearest UPS feeder & by installing single phase 11 KV ,10 KVA distribution
transformer.
(b) At the 1st stage the erection of 11 KV single phase
lines and installation of single phase transformers will be completed by RE/APDRP
Organisation and the remaining LT work i.e installation of energy meter and
laying of services will be carried out by respective DS Sub-Divn. of the
concerned area.
The existing
instructions as contained in CC 22/02 dated 31.5.2002, CC 58/03 dated 26.8.03 & 20/04 dated 19.4.04 shall stand amended to the above extent.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.64/2006
Memo
No.79414/80214/SSM-451-A/Vol.II
Dated.
29/11/06
Sub: One
Time Settlement offer for all categories of permanently disconnected
defaulting consumers.
As per instructions issued vide CC: No. 16/06 dated 17.04.2006, the One
Time Settlement (OTS) package introduced vide CC: No. 42/2002 dated 12.08.2002
was available upto 30.9.2006, for reconnection of various categories of
consumers, whose connections were disconnected temporarily/permanently upto
31.3.2005.
In view of the encouraging
response of the consumers, the matter has been considered and it has been
decided to extend the One Time Settlement package upto 31.03.2007 for
revival of sick Industry and other categories of consumers. With this
extension, the consumers whose connections stand disconnected temporarily
/permanently upto 30.09.2005 can opt for reconnection upto the validity of the
scheme i.e. 31.03.2007.Field Officers are requested to give vide publicity to
the above instructions.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.63/2006
Memo
No. 78267/79067/DSA/Vol.I/Comml.
Dated.
27/11/06
Sub: Constitution of State/Zonal Level Dispute Settlement Committees of
PSEB.
In partial modification to the
instructions circulated vide CC No.4/2005 dt. 14.1.205 and in continuation to
CC No. 29/05 dt. 5.5.05 the nomination from industry on the panel of Circle
Dispute Settlement Committee of Operation Circle, Mohali appearing at A(iv)(1),
Page 2 of the Annexure has been
amended to read as under :-
Page
2, A
(iv)(1), Sh. Balbir Singh, President, Mohali
Industries Association, MIA Bhawan,
Bay No. 143-144, Opposite ESI Hospital, Industrial Area, Phase VII, SAS Nagar,
Mohali-160055.
All other provisions of the CC
No.4/2005 dated 14.01.2005 & CC No.29/05 dated 5.5.05 shall remain
unchanged.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No 62/2006
Memo No. 77375/78125/CC/T/11/L
Dated : 22.11.06
Sub:- Review of General Conditions of Tariff of Seasonal Industries and consequential review of Tariff order for the year 2006-07.
PSEB
vide CC No. 20/2006 DT. 12.5.2006 and CC 36/2006 dt. 14.7.2006 has revised the
tariff for Seasonal Industries w.e.f. 1.4.2006 and the General Conditions of
Tariff & Schedule of Tariff on
the directions of
Punjab
State
Electricity Regulatory Commission. As per above instructions reduced MMC was
leviable for the off season period for the months of March to August. Punjab
Rice Millers Association (Regd.) and
Punjab
Cotton Factories and Ginners Association (Regd.) petitioned PSERC against levy
of MMC during off season period.
PSERC
after considering the petition and hearing the view point of PSEB & Rice
Miller Association has decided vide order No. PSERC /Reg. 153/6752 dt.
31.10.06 that the General Conditions of Tariff made applicable by the commission with effect from 1.4.2006 shall not
apply for the financial year 2006-
07 in
so far as Seasonal Industries are concerned and the instructions in this
respect as applicable before the issue of General Conditions of Tariff will continue to apply for the financial year 2006-07. So for seasonal
Industries the tariff as was applicable prior to 1.4.2006 would remain
applicable for the financial year 2006-07. Necessary action may be taken
accordingly.
It
is also requested that wide publicity may be given for the information of the
concerned consumers please.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C. No.61/2006
Memo No. 76213/77013/ SSM-414/TW
/Policy-06-07
Dated.20/11/06
Subject:- Tubewell Policy- Release of tubewell connection under General Category-
Amendment thereof .
On
the basis of feed back from the field officers, instructions were issued vide
CC No.58/06 dated 3.11.06 that in the Operation Divisions, where no AP T/W
application, registered upto 31.3.88 under General Category was pending, new
AP T/W connections under General Category would be released against the test
reports received against applications registered upto 31.3.90 in the order of
seniority based on the date of registration of application and the material for the release of these
connections would be issued by the Stores Organization subject to
certification by the concerned Sr.Xen/Addl.SE on the indent itself that no T/W
application registered upto 31.3.88 under General Category is pending under
his Division. The Operation Divisions where applications registered upto
31.3.88 under General Category were still pending for release of connection,
all out efforts are to be made by the field officers to clear such pending
applications registered upto 31.3.88 and thereafter action should be taken as above regarding release of new AP connections under General
Category against applications
registered upto 31.3.90.
The matter has been reviewed further and
it has been decided that the
cut-off date for release of new AP tubewell connections under General Category
in respect of operation divisions where no AP T/W application registered upto 31.3.88 under General Category is
pending, shall be 31.12.90 instead of 31.3.90
All
other terms & conditions of CC
No. 58/06 dated 3.11.06 shall remain unchanged.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 60/2006
Memo No. 74287/75087/Indl./SNG/55
Dt. 14.11.06
Sub: Non-availing of Full sanctioned load at the time of release of new
Connection –Amendment to ESR 35.
Clarification has been sought by field offices regarding applicability
of ESR Clause 35 titled "Non availing of full sanctioned load at the time
of release of new connection" for the cases involving extension in load on the plea that the Regulation is applicable for release of new
connections sonly.
Upon ,consideration of the after
it has been observed that the instructions are not clear as to whether these
are applicable to new connections only or to cases of extension in load as
well it is also felt that extension n load involves addition of new
equipment/machinery which is; equivalent to installing load of new connection
for all intent and purposes. Thus ,it is very much logical that the facility
of; building up of the load in phases as per instructions of ESR clause 35
should also be applicable for cases involving extension inn load.
The matter has been considered by the WTMs and it has been decided to
incorporate a new clause 35.1.3 in the PSEB Electricity Supply Regulations as under:
"The provisions contained in ESR clause 35.1.1 and 35.1.2 shall be
applicable for release of extension in
load also ,to those LS consumers ;whose connected load including applied
extension in load is more than 1 MW"
All other terms and conditions as applicable as per ESR 35 shall remain
unchanged.
Sd/-
Director/S-II
PSEB,Patiala.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C. No. 59/2006
Memo No. 73295/74095/SSM-414/Drip
Dated.10/11/06
Subject:- Release of tubewell connections on
priority to the farmers installing Drip/ Micro Sprinkler Irrigation system.
The present water scene of
Punjab
is pointing towards the repid degradation of ground water resources. The
ground water table decline has crossed
30 cm
annually and more than 100 blocks of the state have suffered groundwater
degradation of more than 100% . Thousands of tubewells in the state have been
forced to be converted from centrifugal to submersible pumping even in this
era of power shortage. In the long
run, ground water conservation is the only alternative to restrict this
dangerous trend of ground water level decline.
The Government of India has launched National Horticulture Mission (NHM)
for holistic development of
horticulture in the country . Another programme of Micro Irrigation (MI &
Drip/Sprinkler System) of horticulture has been launched. To encourage water
conservation by using drip/sprinkler irrigation system and in the best
interests of the farmers & State, a meeting regarding allowing priority
power connections to the farmers installing drip/micro sprinkler irrigation
system under the above two programmes launched by the Government of India was
held on 21.7.2006 under the Chairmanship of Chief Secretary ,Punjab. As per
decision taken in the meeting , the matter has been considered and it has been
decided as under:-
i) Release of tubewell connections on priority shall be allowed to the prospective consumers in the State on Drip/Micro Sprinkler Irrigation Systems installed on a minimum area of 2(two) hectares for fruit crops,
and 1(one) hectare for vegetables
and non horticulture crops.
ii) The Priority shall be allowed on a Joint Certificate from the
Divisional Soil Conservation Officer and the Deputy /Assistant Director of
Horticulture.
iii) The tubewell connection will be released after the installation
of the Drip/Micro Sprinkler Irrigation System.
iv) The priority shall be admissible upto the release of connection
without any cut off date subject to following terms & conditions.
a) The
prospective consumer must have land in his own name and will submit FARD in
this regard at the time of registration of application.
b) Only One tubewell
connection shall be allowed under this priority category.
c) The
prospective consumer shall submit an affidavit duly attested by First Class
Magistrate that in case he is found using the tubewell connection for any
other purpose, his tubewell connection shall be disconnected without any
notice.
d) The priority
shall be allowed by Sr.Xen/Addl.SE/Op. concerned after fully satisfying
himself with regard to the genuineness of the priority claim & that the
prospective consumer has actually installed the sprinkler system.
e) The consumer
should purchase ISI marked material for drip irrigation/sprinkler system
through demand draft with valid receipt. The equipment so purchased shall be
clearly identified with Sr.No. and Make etc. on the bill itself. The material
should be duly tested / approved by National Test House/ any other
agency/Govt. approved agency or duly
recommended
and tested & approved by Punjab Agricultural University Ludhiana and
Punjab Small Scale Industrial
Corporation.
f) The concerned Divisional Soil Conservation Officer/Dy.Director
Horticulture, as the case may be, must certify after installation of Drip
irrigation/Sprinkler system at site, that material procured is ISI marked duly
tested by the approved Test House/Govt. Agency and system as a whole has been
installed on a minimum area of two hectares for Fruit crops & one hectare
for Vegetable & Non-horticulture crops and is of approved design / layout
.
g) To avoid misuse of
the priority, the test reports relating to drip irrigation / sprinkler system
shall be verified by the AE/ AEE/Xen/Op. only. The concerned officer at the
time of verifying the test report must record on the test report itself that
the prospective consumer has installed proper/ valid sprinkler system
indicating the Sr. No. & other details of the equipment installed on the
test report itself.
h) The working of
the Drip Irrigation/Micro Sprinkler system shall be checked by the AE/ AEE/Xen/Op. concerned once in a year and a certificate of checking shall be placed
in the consumer file so as to ensure that the system is in the working order
and this priority is not being misused. In case it is found on checking that
this priority is being misused, the tubewell connection shall be disconnected
on the spot without any notice.
i) ESR No.13.4.18 & 13.4.18.1 & & 13.6.18.2 are amended accordingly.
Procedure / roster to be followed by field officers for the release of
AP tubewell connection / issue of material had been circulated vide CC.No.
43/2006 dated 4.8.2006 and for restoring this facility of allowing priority
tubewell connection to prospective consumers adopting Drip/Sprinkler System,
the procedure/roster is amended as under : -
i) 1st - General Category
ii) 2nd - General Category
iii) 3rd - General Category
iv) 4th - Ex-servicemen
priority
v) 5th - Kandi Area
priority
vi) 6th - Own
transformer priority
vii) 7th - Drip/Sprinkler
System priority
viii) 8th - General
Category & so on.
It
is requested that wide publicity may be given by the field officers for
information of general public.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.
58/2006
Memo
No. 71737/72537/SSM-414/TW-06-07
Dated.3.11.2006
Subject:- Tubewell Policy- Release of tubewell connection under General Category.
Instructions were issued vide CC No.25/06 dated 2.6.06 that all out
efforts should be made by the field officers to clear the AP T/W applications
registered upto 31.3.88 under general category and issue of material for
release of new AP T/W connections was allowed in respect of test reports
received against applications registered upto 31.3.88 only in the order of
seniority based on the date of registration of application. An amendment was
issued vide CC No.42/06 dated 3.8.06 and the instructions were also reiterated
in the T/W policy for the year 2006-07 issued vide CC No.43/06 dated 4.8.06.
There
is a feed back from the field officers that in the Border, North & Central
Zones, there are no pending T/W applications under general category registered
upto 31.3.88. In the West &
South Zones also in many of the Divisions, there are no pending applications
under general category registered upto 31.3.88. Thus in view of above
instructions the release of new T/W connections in the Border, North &
Central Zones and some of the Divisions under West & South Zones, has been
held up. The matter has been reviewed and it has been decided as under:-
i) In the Operation
Divisions, where no AP T/W application, registered upto 31.3.88 under General
Category is pending, new AP T/W connections under General Category shall be
released against the test reports received against applications registered
upto 31.3.90 in the order of seniority based on the date of registration of
application.
ii) The Operation Divisions where
applications registered upto 31.3.88 under General Category are still pending
for release of connection, all out efforts shall be made by the field officers
to clear such pending applications registered upto 31.3.88 and after the
backlog of applications registered upto 31.3.88 is cleared, action shall be
taken as per Para- (i) above.
iii) The material for the release of
connections under General Category against applications registered upto
31.3.90 shall be issued by the Stores Organization subject to the condition
that a certificate is given by the concerned Sr.Xen/Addl.SE on the indent
itself that no T/W application registered upto 31.3.88 under General Category
is pending under his Division.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.
57/2006
Memo No. 70819/71619
/ SSM-249/VDS/SP
Dated: 3/11/2006
SUB:- Voluntary Disclosure Scheme for S.P. consumers.
To regularize the already running unauthorized load of SP Category Consumers so that the feeding system of PSEB could be upgraded in
commensurate with the already running load, thus ensuring continuity of the
quality power supply, it has been decided to introduce VDS for Small Power
supply (SP) consumers only w.e.f. 7.11.06 upto 31.1.07 with the following terms and conditions :-
(i) No load surcharge shall be charged during the period the scheme shall
remain operative.
(ii) The load shall be deemed to have been released from the date of written
declaration indicating the extra load installed by the consumer. This written
declaration shall be considered as the A&A form for the enhanced load and
kept in the consumer case file and suitable entry shall be made on the
existing A&A form. The small power industrial consumer shall be allowed to
declare the additional load to the extent of 100% of the existing sanctioned
load.
(iii) SCC at half the normal rate
of Rs.750/-per KW i.e. Rs.375/- per KW shall be recovered for the additional
load
(iv) ACD at the prevalent rate of Rs.500/-or part thereof per KW for extra
load shall be recovered in case of no change of category after extension.
(v) In case of change of category from SP to MS as a result of
additional load, the ACD as
applicable under MS category i.e. Rs.750/- per KW or part thereof shall be
recovered for the total load giving due credit for the ACD already deposited.
(vi) As a result of change of category due to increase in load, consumer
shall be governed under the tariff applicable to the changed category from the
date of declaration of load.
(vii) The load shall be checked/verified by the AE/AEE/XEN (OP.) subsequently
& consumer will be given a period of six months for installation of shunt
capacitor of requisite capacity if required.
(viii) Wherever augmentation of line is involved, the same shall be done by
the Board on priority.
(ix) The release of load under VDS shall be further subject to condition
that the consumer shall submit an affidavit for submission of NOC for his
total load from the PPCB within six months of declaration of extended load, if
the same is applicable to his industry to be decided by load sanctioning
authority.
Similarly NOC from Municipal Corporation/Committees, and PUDA shall not
be insisted upon from such consumers, whose industry is already running in the
residential areas or other restricted areas subject to the condition that if
any statutory body or courts objects later on for the extension so granted,
PSEB shall be at liberty to withdraw the extension for which suitable
undertaking may be taken from the consumer. However, such consumers shall be
required to deposit ACD at double the normal rates for the extended load only. In case of change of
category from SP to MS, the ACD for the existing load shall be charged as per
MS category after giving due credit for the ACD already deposited and for the
extended load, the ACD shall be charged at double the normal rates for MS
category.
(x) This scheme shall not be available to the consumers located in
Chandigarh
periphery area.
It is requested that wide publicity may be given by the field
officers for information of general public.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 56/2006
Memo
No. 69540/70340 /CC/T/1/Misc./SC
Dated : 31.10.2006
Sub:- Grant of free electricity for domestic purposes up to 200 units per
month to the Members of Scheduled Castes having sanctioned load up to 1000
Watts.
As per instructions issued vide CC No. 11/2006 dt. 1.3.2006 SC domestic
consumers with connected load upto 500 Watts were allowed free electricity
upto 200 units per month w.e.f. 1.9.05. In compliance of instructions issued by Govt. of
Punjab
received vide Chief Secy. GOP note
dated 11.10.06, it has now been
decided to grant concession of free electricity upto 200 units per month to SC
DS consumers with connected load upto 1000 Watts w.e.f. 2.10.2006. Accordingly
w.e.f. 2.10.06 the SC consumers with connected load above 500 Watts and upto
1000 Watts have also become eligible for free electricity upto 200 units per
month.
It has further been decided that w.e.f. 2.10.06, meter rental, MCB
rental, Service charges and octroi
etc. will also not be charged in the energy bills of the SC domestic consumers
with connected load upto 1000 Watts i.e. if any SC DS consumers with connected
load upto 1000 Watts has his consumption upto 200 units per month or 400 units
bi-monthly, his bill amount will be zero.
Necessary action should be taken accordingly and it should be ensured
that concession is passed on to the eligible consumer, during the current
billing cycle of October, November 2006. All the instructions issued vide CC
No. 11/2006 for allowing free electricity to SC DS consumers with connected
load upto 500 Watts will be applicable except that limit of connected load has
been increased to 1000 Watts w.e.f. 2.10.06.
Following points may be kept in view :
(i) Refund in cash to remaining SC DS
consumers with connected load upto 500 W on a/c of free electricity upto 200
units per month w.e.f. 1.9.05 may continue to be given as per instructions
issued vide CC No. 17/2006 and CC 32/2006.
(ii) Free electricity with 200 units per
month will also be admissible to new SC DS consumers with connected load upto
1000 W from the date of connection.
Field Officers
are requested to give wide publicity of the above concession being provided by
the Board so that maximum number of eligible consumers are in a position to
avail of the same. Advertisement is being given in various news papers
requesting the eligible consumers to submit requisite documents to concerned
subdivisions. It should be ensured that intimation on the prescribed performa.
(Advice) is sent to the CSC immediately on receipt of requisite documents from
the consumer.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC: No 55 / 2006
Memo
No. 68576/69376/ SSM-249/VDS/DS
Dated:
31.10.06
Subject: Voluntary Disclosure Scheme (VDS) for DS /NRS category of consumers.
In view of the over
whelming response to the VDS for DS and NRS consumers introduced vide CC
No.45/05 dated 12.7.05 and the feedback, from field offices that unauthorized
load of DS/NRS consumers is
resulting into overloading of the system and frequent breakdowns especially
during summer season, the matter has been considered & it has been decided
to introduce the voluntary disclosure scheme for DS & NRS consumers w.e.f
1.11.2006 so that DS/NRS consumers may declare their unauthorized load & get it regularized to enable PSEB to augment the system in line with the
increased load.
The VDS for DS & NRS consumers shall remain in force for
three months i.e upto 31.1.2007.
2. The main features of
this scheme shall be as under :-
i) There will be no checking of connected load
during the period VDS remains in force and resultantly no penalty for
unauthorized extension in load shall be levied.
ii) The load shall be computed as under :-
Description |
Domestic |
NRS |
Remarks |
Light
Point |
60
Watts (1/2 of total light points to be taken into account) |
80
Watts |
Fraction
of Light Point to be taken as one |
Fan
Point |
80
Watts each
(1/3rd
of total No. of sockets to be taken into account) |
100
Watts each |
Fraction
of Fan Point to be taken as one. |
Wall
Sockets |
60
Watts each (1/4th of total No, of sockets to be taken into
account) |
80
Watts each (1/3rd of total No. of sockets to be taken into
account) |
Faction
of Socket to be taken as one socket. |
Power
sockets |
1000
Watts each
(1/4th of total No. Sockets to be taken into account) |
2000
Watts each (1/2 of total No. of sockets to be taken into account) |
Faction
of Socket to be taken as one socket. |
i) After
computing the load as above, the consumer can intimate the computed load for
regularization on the reverse of the energy bill also, which will form part of
A&A form and placed in consumer file. During the VDS period, the load will
be regularised without any verification and test report.
ii) The extra load shall be regularized in the name of existing consumer, may
be owner of the premises or tenant or actual user as the case may be without
asking for any additional documents for effecting change of name or for
establishing identity of the original consumer.
iii) Mass awareness camps shall be arranged
where the concerned Officers/Staff of DS organization shall be available to the
public in the said Camps for regularization of extra load on the spot after
accepting payment of ACD and reduced SCC there & then.
iv) Reduced Service Connection
Charges (by 50%) shall be recovered against such declaration as under:-
SR.No. |
Load |
DS
(Rs.per KW) |
NRS
(Rs.per KW) |
I |
Upto
1KW |
Rs.125/- |
Rs.125/- |
II |
Above
1KW & upto 3KW |
Rs.150/- |
Rs.250/- |
III |
Above
3KW & upto 7KW |
Rs.250/- |
Rs.375/- |
IV) |
Above
7KW |
Rs.375/- |
Rs.500/- |
vii) ACD recoverable shall be as per existing rates which are as under:-
a) Domestic Rs.500/-per KW or part thereof.
b) Non Residential (NRS)
Rs.700/-per KW or part thereof.
viii) Augmentation of
service line/transformer and the power system and change of meter etc. shall be
done by the Board at its own cost.
ix) After extension in load, if
load falls in range from 11KW to 50 KW the connection shall be released with LT
metering in 3 phase category by providing independent T/F of 10/16 /25 /63KVA or
higher capacity with zero LT and meter shall be installed in MCB or pillar box
on the pole /under the distribution transformer. However more than one
connection can be given from the same T/F if the premises are nearby by
providing meters in pillar boxes or in MCB /CT Chambers on poles.
For loads ranging from 51 KW to 100 KW shall be released at 11 KV only
with LT metering by providing independent 63 /100/200 KVA distribution
transformers. DS/NRS loads above 100 KW shall continue to be released as per
existing instructions as per Schedule of Tariff SV and SVI, at 11 KV supply
voltage as per discretion of the Board
x) No load surcharge shall be levied.
xi) The
total load(including unauthorized extension) shall be considered for the purpose of regulating service connection charges in the specific
slabs mentioned above, but the actual charges to be recovered shall be for the
unauthorized load only at the rates as
applicable for the slabs relating to the total load.
xii) DS/NRS consumer shall be allowed to extend their load under VDS subject
to maximum of 100% of the sanctioned load .
xiii) In case of new connections released under DS/NRS category , no extension
in load under VDS shall be allowed for a period of 6 months from the date of
release of connection .
The field officers shall give wide publicity to the scheme for information of the General Public.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.54 /2006
Memo No.
67173/67973 /SSM-249/AP.
Dated: 20.10.2006
Sub: Voluntary Disclosure Scheme vis-à-vis compulsory regularization of unauthorized extension in load by Agriculture Tubewell
consumers.
Feedback has been received from
the field offices that due to depleting water table, No. of AP consumers have installed higher capacity motors
thus putting excess load on the system which loads to higher losses, and overloading/ breakdowns in the system . It would, therefore, be in the
interest of the Board that the unauthorized load of AP consumers is regularized
after recovering appropriate charges. Moreover, there is demand from the various Kissan Unions also that VDS for AP consumers, on
the pattern as introduced vide CC
23/2006 dated 26.5.2006, should be
re-introduced .
2. The matter has been considered and it has been decided to introduce the
VDS for AP consumers under which they will be able to voluntarily disclose /
declare their excess / unauthorized load & get the same regularized after
paying requisite charges as per VDS . The scheme will
remain inforce from 1.11.2006 to 31.1.2007.
3. The charges for regularization of the excess / unauthorized load so declared under VDS
shall be Rs.1000/- per BHP as Service connection charges and Rs.200/- per BHP as
ACD,without levy of any load surcharge.
4. The temporary
tubewell connection released during the paddy season of 2005 and regularized as
per CC No. 9/2005 shall not be covered under this scheme as no extension in load
is permissible to such regularized tubewell connection upto a period of 3 years
from the of release /regularization of such a temporarily tubewell connection.
5. Salient features of the scheme shall be as under:-
(i) The regularization shall be done immediately as
deemed regularization on detection of unauthorized load or self-declaration by
the consumer regarding unauthorized load. It is emphasized that the farmers who
visit the sub divisional offices for regularization of the additional load
should be attended properly and promptly. His application regarding declaration
of the additional load be accepted and necessary entries of the additional load
be made in his passbook and ledger and the BA-16 Receipt issued for the charges
recovered. The consumer shall install the shunt capacitors of requisite capacity
as per the total load and the test report shall be arranged by SDO Incharge
through JE Incharge who should indicate total load of the motor and KVAR
capacity of the Shunt Capacitor installed. The requirement of new forms has
been dispensed with. The extra load shall be regularized after deposit of
requisite charges for extended load only and getting suitable entry made in the
passbook.
(ii) Augmentation of the line
and distribution transformer, wherever required after due consideration /
verification by Sr.XEN/Op. concerned shall be done by PSEB at its cost. For the
purpose of regularization of the load, the loading of the transformers may be
taken as 100% instead of the existing 80%. In case with the addition of
unauthorized load , the loading of the existing transformer becomes beyond 100%
the action to augment the transformer capacity shall be taken with the approval
of SE/DS as under :-
a) 25/63
KVA transformers which become more than 100% loaded shall be replaced with 63
KVA/100 KVA transformer respectively with the condition that neither a new tubewell connection shall be released from this transformer
nor any tubewell connection from other over loaded transformer shall be shifted
to this augmented transformer .
b) In case
of 100 KVA transformer, the de-augmentation shall be done by providing small
individual transformers of 6.3/10/16 KVA rating .
The regularization of unauthorized load shall not be withheld due to over
loading of distribution transformers as the unauthorized hidden load was already
on the system . [
Field officers are requested to give wide publicity to this
scheme and organize mass consumer contact camps in rural areas to regularize the
higher capacity motors on the spot during the VDS period.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.53/2006
Memo
No..65412/66212/SR 134.5
Dated:17.10.2006
Sub: Commercial Circular No.34/06 dated 6.7.2006 – Clarification thereof.
An open house discussion
with the field officers under the Chairmanship of Member/D was held and it has been decided to issue following clarifications/
amendments to the Commercial Circular No.34/06
dated 6.7.06:-
1. Keeping in
view the problems faced by the field officers in dealing with the theft of
energy cases, the matter has been considered and it has been decided that
checking regarding theft of electricity be carried out by the following
officers/officials of the Board:-
1. |
All domestic/ NRS/AP /SP /BS connections upto 20 KW |
JEs/AAEs of Operation Wing( within his jurisdiction). |
2. |
All domestic/ NRS/AP /SPMS/LS/BS connections upto 500 KW |
Any officer of operation wing not below the rank of AE( within his jurisdiction). |
3. |
All Large & Bulk Supply beyond 500 KW and Railway
Traction |
Any officer of operation wing not below the rank of Sr.Xen ( within his jurisdiction). |
| |
Enforcement Officers: |
|
1. |
All categories of consumers with loads upto 500 KW |
Any Officer of the Enforcement Wing not below the rank of
AEE( within his jurisdiction). |
2. |
All categories of consumers with loads above 500 KW |
Any Officer of the Enforcement Wing not below the rank of
Sr.Xen( within his jurisdiction). |
| |
MMTS Officers: |
|
| |
Medium Supply / Large Supply / Bulk Supply. |
Sr,Xen/Addl.SE/MMTS |
Since special courts for
dealing with the cases of theft of energy as covered Under Section 153 of
Electricity Act-2003 are yet to be constituted by govt. of Punjab, as such after
carrying out the inspection of the premises, authorized officer shall prepare a
detailed inspection report containing details of connected load, meter/metering
equipment details, working of meter, condition of seals and other irregularities
noticed (such as any artificial means of theft of electricity).
The authorized officer
and other members of the team accompanying him shall carry photo identity cards.
The inspection report shall be signed by the authorised officer, all members of
the inspection team and consumer/person or his/her representative. A copy of the inspection report shall be handed over to the consumer/
person or his/her representative at site under proper receipt. In case of refusal by the consumer/ person or his/her representative, a
copy of the inspection report shall be pasted at a conspicuous place in/outside
the premises. Simultaneously, the
inspection report shall be sent to the person under registered post.
In case the theft of
electricity is established, the supply of such premises shall be disconnected
forthwith and meter/metering equipment shall be sealed in 'as found conditions'. in order to take further action in view of the circumstances explained
above, a copy of the inspection report shall be sent by the authorized/checking
officer/official to the concerned assessing officer for making assessment of
charges as per provisions of Section 126 of Electricity Act-2003.
As per notification No.
1/60/03-EB(PR)/1186 dated 27.12.04 of the Govt. of Punjab, the following
officers of the Board are authorized to make assessment of charges payable by
the LT & HT consumers:-
Category of consumers |
|
Assessing Officers |
All HT
consumers above 1 MW load |
: |
CEs of the Operation Wing of respective Distribution Area |
All HT Consumers upto 1 MW load |
: |
SE/Dy.CEs of Operation Wing of the Distribution Area. |
All LT Industrial consumers |
: |
Sr.Executive Engineers/Addl/SEs of Operation Wing of the
Distribution Area. |
All other LT consumers. |
: |
Assistant Engineer/Assistant Executive Engineers/Executive
Engineers of Operation wing of the Distribution Area. |
2. Unauthorised use of electricity (UUE) under section 126 of the
Electricity Act-2003.:
The UUE shall be dealt
as per Section 126 of the E.A.2003 and covers the following means:-
(i) by any artificial
means , or
(i) by a means not
authorized by the concerned person or authority or licensee, or
(ii) through a
tampered meter, or
(iii) for the purpose
other than for which the usage of electricity was authorized.
Following types of cases shall also be covered under
UUE:-
(a) Where a consumer
engages un-authorizedly in supply of electricity to any service disconnected by
the Board/Licensee or in the illegal restoration of his own service disconnected
by the Board/Licensee.
(b) Where a consumer
keeps connected to Board/Licensee's supply system any apparatus or adopts any
electrical appliance for the purpose of splitting the phase to run his three
phase appliances when the Board/Licensee's three phase supply is not available
to him.
(c) Where a consumer
uses electricity supplied under a particular tariff for a purpose for which some
other (especially higher) tariff is in-force, or
(d) Where a consumer
without the permission of the Board/Licensee extends the Board/Licensee's supply
to any premises other than the premises to which the supply is given or to any
consumer/unit within the same premises. Provided
that extension of Board/ Licensee's supply for a religious or non commercial
social function of the consumer himself not exceeding three days shall not be
considered as unauthorized use of electricity.
3. Procedure for booking a case for unauthorized use of electricity.
(a) An
assessing officer, (designated as per GOP notification dated 27.12.04 and
detailed under para-1 above, suo moto or on receipt of reliable information/
complaint regarding unauthorized use of electricity in a premises shall promptly
conduct inspection of such premises.
(b) The assessing officer and other members of the team shall carry along
with them photo identity cards, which shall be shown to the person present at
the premises before entering therein.
(c) If on inspection of the premises or after inspection of the equipments,
gadgets, machines, meter etc. or after inspection of the records, the assessing
officer comes to the conclusion that the person is indulging in unauthorized use of electricity,
he shall prepare an inspection
report giving details of connected
load, condition of seals, working of
the meter and also mention the irregularities noticed which established
unauthorized use of electricity.
(d) Details
of evidence substantiating the unauthorized use of electricity in the premises
shall be clearly recorded by the assessing officer in the inspection report.
(e) The inspection report shall be signed by the assessing officer and each
member of the inspection team and the person or his/ her representative, and handed over to the person or his/ her representative
present at site, under proper receipt. In
case of refusal to accept the report, a copy of the inspection report must be
pasted at a conspicuous place in/outside the premises. Simultaneously, the
inspection report shall be sent to the person under registered post.
(f) The assessing officer shall provisionally assess to the best of his
judgement the amount to be paid by the person benefited by the use of
unauthorized use of electricity.
(g) The
order of provisional assessment under section-126 of the Electricity Act -2003
(as per proforma enclosed) shall be served upon the person under proper receipt
through registered post or courier or
speed post or by hand (indicating the identity of the person to whom delivered).
(h) The person served with the order of provisional assessment may accept
such assessment and deposit the assessed amount with the licensee within 7 days of such provisional assessment order
served on him, and in that case, he shall not be subjected to any further liability or any action by any authority whatsoever.
(i) The reply to the notice of provisional assessment order shall be
submitted by the person within 7 days of
its receipt. The assessing officer, only after affording a reasonable
opportunity of hearing to such person, shall pass a final assessment order specifying the amount
payable by such person on account of unauthorized use of electricity.
4. Submission of reply by the person:
If
the person submits his reply within the stipulated period, the assessing officer
shall analyze the case within 7 working days from the date of submission of
person’s reply, after carefully considering all the submissions and documents
submitted by the person, facts on record and the inspection report. The case of
unauthorized use of electricity shall be dropped immediately, if it is concluded
by the assessing officer that there
is no unauthorized use of electricity, and the decision in this respect shall be
communicated to the person under proper receipt, within 15 days of submission of
reply by the person.
5. Affording personal hearing to the person. (Levy of charges for UUE):
(a) If the assessing officer concludes that there is unauthorized use of
electricity, he will provide personal hearing to the person within 15 days of
submission of reply and will pass a
final order of assessment specifying the amount payable by the person
, only thereafter.
(b) If the assessing officer reaches a conclusion
that the unauthorized use of electricity
has taken place, it shall be presumed
by the assessing officer that such an unauthorized use of electricity has been continuing for a period of 3 months immediately preceding the date of inspection in case of domestic and
agricultural consumers and for a period of 6 months immediately preceding
the date of inspection for all other categories of
consumers, and he shall provisionally assess the consumption per month
based on the following formula:-
(A) For cases of unauthorized use of electricity covered under sub-section
6(b)(i),(ii) and (iii) of Section 126 of the Act:-
(1) Units assessed = L x D x H x F,
where L is the load found connected during the course of inspection in KW.
D
is number of working days per month, during which unauthorized use/theft/pilferage is suspected and shall be taken
for different categories of use as below:-
a) |
Continuous industry |
30 days |
b) |
Non-continuous industry |
25 days |
c) |
Domestic use |
30 days |
d) |
Agriculture |
30 days |
e) |
Non-Residential(Continuous) viz hospitals, hotels,
restaurants, guest houses, nursing homes, petrol pumps. |
30 days |
f) |
Non Residential (general)i.e. other than (e) |
25 days |
g) |
Water works & Street Lights |
30 days |
h) |
Other categories. |
30 days |
H
is use of supply hours per day, which
shall be taken for different categories of use as below:-
a) |
Single Shift industry(day/night only) |
08 hrs. |
b) |
Non-continuous process industry(day/night) |
20 hrs. |
c) |
Continuous process industry |
24 hrs. |
d) |
(i) Non
Residential(General) including restaurants)
(ii) Hotels, Hospitals, nursing homes, guest houses, petrol pumps. |
12hrs.
20 hrs. |
e) |
Domestic |
08 hrs. |
f) |
Agriculture |
06 hrs. |
g) |
Water works |
08 hrs. |
h) |
Street Lights |
12 hrs. |
| |
Other categories. |
12 hrs. |
F
is load factor,
which shall be taken for different categories of use as below:-
a) |
(i) Industrial (General)
(ii) Power Intensive, Arc Furnace |
60%
75% |
b) |
Non-Residential |
60% |
c) |
Domestic |
40% |
d) |
Agriculture |
100% |
e) |
Direct Theft |
100% |
f) |
Other categories. |
100% |
(2) The
consumption so assessed as above shall be charged i) for a period of 3 months in
case of domestic and agriculture supply consumers and for a period of 6 months
in case of other consumer categories, ii) at one and half times the rate per
unit of the tariff applicable to the consumer category, after adjusting the
amount paid by the person for the energy consumption for the assessment period
if any.
(3) In cases
where fixed monthly tariff exists, monthly assessment shall be made at one and a
half time the monthly rate.
(B) For cases of unauthorized use of electricity covered under sub-section
6(b)(iv) of section 126 of the Act.
(i) If it is established during inspection of a premises that the energy
supplied is used for a purpose on which higher tariff is applicable, the total
energy consumed in the previous 3 months in case of domestic supply or
agriculture consumer and 6 months for all other category consumers, from the
date of detection, shall be charged at one and half times the rate applicable
for the category for which load was found to have been used.
(ii) The above calculations are subject to the condition that meter is
recording energy accurately. Else,
the energy will be calculated on the basis of LDHF formula as per details in A-1
above.
(iii) The amount already paid by the person for the energy consumed during the
assessment period, if any, shall be adjusted in the amount assessed as above.
(iv) This assessment shall not relieve the consumer from any penalty imposed
by law/regulations or under any provisions of the code.
The
period of 3/6 months may be suitably reduced if it is established from the facts stated by the person at the time of
inspection or any other such
evidence noticed by the assessing officer that the offence has been committed
for less than 3/6 months respectively. However, the assessing officer shall duly
record reasons for reduction in the period of such provisional assessment. The
amount shall be assessed at a rate equal to one and a half times the tariff
rates applicable for the relevant category of consumers. Credit for the
amounts, if any paid by the person during the period for which the assessment is
made shall be allowed, to avoid duplication of billing for such period.
In case of seasonal industries, the off-seasonal
period (non-working) shall not be included in the period under assessment.
For AP consumers the tariff rate without Govt. subsidy
shall be applicable for assessment of charges.
(c) The person will be required to deposit the assessed amount with the
licensee within 7 days of receipt of the final order of assessment. The licensee may, after taking into consideration the financial position
and other conditions of person, extend the last date of payment or approve the
payment to be made in installments on a written request made by the person and
submission of an undertaking to abide by the schedule of payment along with the interest due as per rules.
(d) The person served with the final assessment order may accept the order
and deposit the assessed amount with the licensee and in that case he shall not
be subjected to any further liability or any action by any authority whatsoever.
6. Appeal to Appellate Authority.
(a) No appeal shall be entertained by
the appellate authority (prescribed as per para-3 of CC 34/06 dated 6.7.2006)
unless the person deposits an amount equal to 1/3rd of the assessed
amount with the licensee and encloses documentary evidence of such deposit along with the appeal. Further, no appeal shall lie to the
appellate authority against the final order of the assessing officer if the
final order is made with the consent of the parties.
Any person aggrieved by the final assessment order made by the assessing
officer may, within 30 days of the
said order, prefer an appeal in such form, verified in such manner and be
accompanied by such fee as specified by the Commission in its Regulations for procedure of filling appeal before the Appellate
Authority to an appellate authority. (PSERC Notification dated 7.3.05 –
Annex-III of CC No. 34/06 dated 6.7.2006)
(b) The appellate authority shall dispose
of the appeal within 90 days of its receipt after hearing
the parties and pass an appropriate
speaking order and send the copies of order to the assessing officer and the appellant. The order of the appellate authority shall be
final. No civil court shall have the
jurisdiction to entertain any suit or
preceding in respect of any order
passed by the assessing officer or
appellate authority.
(c) In case the appellate authority decides that the case of unauthorized use
of electricity is not established, no further proceeding shall be taken against
the appellant and the case shall be dropped.
(d) Where the case of unauthorized use of electricity is established, the
person will be required to make the payment against final assessment order
within 7 days of its receipt.
7. Default in payment of amount assessed.
(a) In case of default in payment
of the assessed amount or any of the
installments of the assessed amount agreed
to by the person or 1/3rd amount in case filling of appeal is contemplated by the person, the licensee shall, without giving
any further notice in writing, disconnect the supply of electricity, remove the
meter and service line.
(b) When a person defaults in making payment of assessed amount, he, in
addition to the assessed amount shall be liable to pay, on the expiry of thirty
days from the date of order of assessment, an amount of interest @16% per
annum compounded every 6 months.
(c) The levy of charges on account of unauthorized use of electricity shall
continue till the cause of levy is removed and verified by the licensee.
8. The
compliance of above instructions should be carried out in letter & spirit. Any
difficulty in the implementation of these instructions may be immediately
brought to the notice of this office through the concerned EIC/CE/DS.
Sd/-
Chief Engineer/Comml,
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.52/2006
Memo No.64057/64857 /SSM-450
Dated: 10.10.2006
Sub: - Release of AP T/W connection to Gram Panchayats for irrigating Gram
Panchayat land on priority.
As per
ESR-13.6.15 one no. tubewell
connection on priority is admissible to Gram Panchayats to enable them to lease
out the Shamlat land of the Gram Panchayat at a higher rate. However, keeping in view the huge backlog of AP test reports, a ban was imposed w.e.f. 12.4.2002 on the issue of demand notices to all AP categories including
Gram Panchayat priority. In a recent meeting
of the Programme Implementation Committee chaired by Hon'ble Dy.C.M., Punjab
held on 10.7.2006 at
Chandigarh
, it was desired that in order to supplement the income of Village Panchayats, tubewell connections may be released by the Board to
Village Panchayats on priority.
The matter has
been considered and Chairman PSEB has been empowered to allow priority (upto the
release of connection ) for a tubewell connection in the
Panchayat
Land
and in the name of Panchayat. However, if panchayat is already having T/W
connection in the
Panchayat
Land
, then another connection will not be sanctioned/released.
The
field officers shall ensure that wide publicity is given to above decision to enable Village Panchayats to make use of
this scheme.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No 51/2006
Memo
No. 63945/64745/C-231/Mohali/L
Dated : 4.10.06
Sub: Waiver of Advance Consumption Deposit on captive power generation -
amendment to Sales Regulation Clause 170.3.2.11.
As per existing instructions if a PSEB consumer is also operating a CPP unit and some of his load is fed from
PSEB supply, he is required to pay ACD for the load exclusively fed from TG /DG set as well. The recovery of ACD for load fed
from TG/DG sets was introduced vide Commercial Circular 26/2002 and incorporated
in sales regulation as ESR 170.3.2.11. Advance
Consumption Deposit is recovered from various categories of consumers at a prescribed rate to safeguard the recovery of
electricity charges of the electricity consumed by a consumer. With the
formulation of captive power policy vide CC 26/02 dated 10.6.02, the co
generator/NRSE project developer as well as CPP owners who were also consumers
of PSEB were required to pay ACD of the load to be fed from co generation plant,
NRSE plant and captive power plant. The logic for recovery of ACD for this load
which is normally fed from the plant is that the plant owner can draw energy from PSEB system for the entire load normally being fed from his own
plant provided the meter and the feeding PSEB line is of adequate capacity. It
has however been noted during the
past years while implementing the captive power policy, that the plant owners do
not resort to drawl of energy from PSEB system to the extent PSEB had assumed.
The energy generated by consumer and consumed by him does not in any way call
for covering the risk of non payment of energy bill for the energy supplied by
PSEB. Therefore, recovering of ACD for the energy consumption for the energy
supplied from the consumer's TG Set is not fair. The matter has been considered
and it has been decided to amend the clause 170.3.2.11 as under:
"Existing consumers or new consumers who wish
to install TG sets as Co generation plant/NRSE plant/CPP and wish to run some
load exclusively from their TG sets as CPP shall not be required to deposit ACD
charges for the load to be run exclusively from the TG sets as CPP. However
permission fee (installation charges) and interfacing (parallel operation)
charges, if any applicable shall continue to be levied. In the event of TG set
load is found running from PSEB system, then load surcharge shall be recovered
for the load found running extra over & above sanctioned load to be fed from
PSEB system. Consumers shall also be liable to pay compensation for damage if
any caused to PSEB lines /equipment. "
Field
Officers are requested to give wide publicity to the above instructions.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC
No.50/2006
Memo
No. 63222/63822/SMI-259
Dated
: 29.09.2006
Sub: Release of Temporary Tubewell Connections during the Paddy Season of
2006.
On the
persistent demand of farmers instructions were issued vide CC No.26/2006 dated
2.6.06 regarding release of temporary tubewell connections during the Paddy
Season of 2006. As per these
instructions, temporary tubewell connections were to remain operational from
20.6.06 upto 30.9.2006 i.e. these are to be disconnected by 30.9.06.
Feedback
has been received from the field officers that during the current paddy season
the temporary tubewell connections were made operational late i.e. w.e.f
20.6.06. Further ,due to late sowing
of paddy by the farmers as per advice of the Scientists from
PAU
, the paddy season will last for another 10 to 15 days and some delegations of
farmers have approached the field officers with the request that temporary
tubewell connections released during the current paddy season may not be
disconnected upto 15.10.06.
In view
of above, the matter has been considered and it has been decided that all
temporary tubewell connections which were released during the current paddy
season as per CC No.26/2006 dated
2.6.06 shall now be disconnected by 15.10.06 instead of 30.9.06. The instructions issued vide CC 26/06 dated 2.6.06 shall stand amended to
this extent and all other terms & conditions shall remain unchanged.
Field
officers are requested to give wide publicity to this scheme through all
possible means including announcements through public address systems of
Gurudwaras/Mandirs etc
Sd/-
Dy.CE/Sales, for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No__49/2006
Memo
No. 66502/67302
Dated
: 19.9.06
Sub:- Load
Surcharge in case of NRS consumers, ESR clause 86.5.0.
As
per Sales Regulation Clause 86.5, if the connected load of a NRS consumer
exceeds the sanctioned load, the excess load shall be unauthorized load and such
excess of the connected load shall be charged load surcharge and the
unauthorized load so detected has to be regularized. Instructions are silent
where marginal load beyond 100 KW is detected and the consumer decides to keep
his load below 100 KW. As per instructions, the consumer is required to pay the
Transformation charges, in addition to service connection charges. The matter
has been considered and it has been decided to introduce Clause 86.5.1 in
continuation to SR clause 86.5 as follows:-
86.5.1. "In the cases
where loads are detected upto 110 KW, the consumer should have option to get the
load regularized or submit fresh Test Reports for reduced load in which case he
would be required to pay only load surcharge for the excess load but ACD,SCC and
Transformation charges would not be leviable. However in case such consumers are
subsequently found to be running load above 100 KW they would not be given any
relief to reduce their load and should then be charged both Transformation
charges as well as ACD & SCC etc. as per provision under Sales Regulations
Clause 86.5. However for load detected more than 110 KW, the existing
instructions shall continue to apply."
All
other terms and conditions of Sales Regulation Clause shall remain unchanged.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 48 /2006
Memo
No. 65449/66249 / Indl.187-KHN
Dated. 15.9.2006
Sub:- Grant of Feasibility clearance to Industrial units.
It
has been observed that in some feasibility clearance cases, the proposal
forwarded by the field office for release of new connection / extension in load
to the prospective / existing consumer is subject to the system constraints such
as commissioning of new 66/132/220 KV S/Stn. or augmentation of the existing
transformer /feeding transmission line which are likely to take long period for
erection /commissioning. Allowing conditional feasibility clearance in such
cases where grid constraints are there for release of load puts the Board in
awkward position as the prospective / existing consumers start putting all sorts
of pressure for release of load and the onus for release of load falls on PSEB
which in turn is unable to do so due to system/ grid constraints .
In view of above, the matter has been considered
and it has been decided as under:-
"Feasibility
clearance for release of new connection/extension in load in case where the
applied load/extension in load cannot be released due to the system/grid
constraints such as installation/augmentation of power T/F or erection of new
Sub-Stn./Transmission line, may not be given. The requisition for these new
connections/extension in load for which feasibility clearance is not given due
to system /grid constraints may be kept pending for consideration for
feasibility clearance until Board is in a position to release the load/extension
in load within a period of six months. However, such applicants shall retain
their seniority as per date of requisition".
The strict
compliance of the above instructions be ensured by all the field officers.
Sd/-
Dy.CE/Sales, for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 47
/2006
Memo No. 57031/65301/SSM-118
Dated. 13.6.06
Sub: ` Consumer Complaint Handling Procedure-
Appointment as Ombudsman.
Punjab
State Electricity Regulatory Commission vide Notification No. PSERC/JSF-29/4523
dated. 30.8.2006 has appointed Smt. Surinder Paul Kaur as Ombudsman in persuance
to Section-42 of the Electricity Act. read with "PSERC (Forum and
Ombudsman) Regulations 2005"(already circulated vide CC No. 27/06 dated
6.6.06). The copy of the Notification dated 30.8.2006 is enclosed herewith for
information of the field officers.
It is requested that the
field officers may give wide publicity to the above for the information of
general public.
DA/As
above.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.46/2006
Memo
No.56645/57445/Tissue Cultutre/Tariff
Dated :
07.09.2006
Sub: Exemption of Electricity Duty to existing Agri. Tissue Culture Units.
The Govt of
Punjab
has decided to grant 50% exemption from payment of ED w.e.f. 18.2.2006 to
existing Agri Tissue Culture units. Accordingly notification No.
11/259/2005-PE-(4)/10155 dt. 3.7.2006 has been issued ,the operative part of
which is reproduced below:-
" In pursuance of the decision of Council of Ministers
taken in its meeting dated 18.2.2006 held under Chairmanship of the Chief
Minister, Punjab and in exercise of the Power conferred by Section 12 of the
Punjab Electricity (Duty) Act, 2005 and all other powers enabling it on this
behalf , the Govt. of Punjab is pleased to grant 50% exemption from the payment of Electricity
Duty which is charged @10% advalorem for a period of 5 year from 18.2.2006 to
the existing Agri. Tissue Culture Units situated in Punjab State and to refund the basic electricity duty already paid by these units
through adjustment in future bills. This exemption has not been granted on
surcharge payable on the basic Electricity Duty. This Electricity Duty exemption
is subject to approval of a transparent metering arrangement by the Supplier and
the Chief Electric Inspector
Punjab
through which the electricity units drawn from the supplier for consumption can
be measured. This is also subject to a certificate of eligibility to be issued
by the Deptt. of Industries/Agriculture.
You are requested to take necessary action in the matter accordingly.
Sd/
Director/Sales-II
For
CE/Commercial,
PSEB
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C
No.45/2006
Memo No. 50400/51200/SSM-118 Dated: 11.8.200
Sub: Consumer Complaint Handling Procedure- Amendment thereof.
Instructions regarding adoption of 'Consumer
Complaint Handling Procedure' as approved by PSERC were issued vide CC
No.40/2006 dated 29.7.2006 followed by CC No.41/06 dated 1.8.2006.
As per
nomenclature approved by PSERC, the various dispute Settlement Committees are
designated as 'Zonal Level Dispute Settlement Committee', Circle level Dispute
Settlement Committee & 'Divisional Level Dispute Settlement Committee'.
However in CC
No.40/2006 dated 29.7.2006 & CC No.41/06 dated 1.8.2006, these committees
were designated as Zonal Level Dispute Settlement Committee(ZLDSC), Circle Level
Dispute Settlement Committee(CLDSC), & Divisional Level Dispute Settlement
Committee (DLDSC). The same may be
replaced to read in line with the nomenclature as approved by PSERC i.e. Zonal Dispute Settlement Committee (ZDSC), Circle Dispute Settlement Committee
(CDSC) & Divisional Dispute Settlement Committee(DDSC) respectively.
2. Nodal Officer (i.e. SE/Dy.CE/HQ Circle of the concerned) as indicated
against Zonal Level Dispute Settlement Committee (ZLDSC), under Para-3 (ii)(a)
of CC No.40/2006 dated 29.7.2006 maybe amended to be read as SE/Dy.CE/HQ
of the concerned Zone .
3. Presenting Officer as indicated against Circle Level Dispute Settlement
Committee(CLDSC), under Para-3(ii)(a) of CC No.40/2006 dated 29.7.2006 maybe
amended to be read as Sr.Xen/Addl.SE/DS
of the concerned Division..
All other terms & Conditions of CC 40/2006 dated 29.7.2006 and CC
No.41/206 dated 1.8.2006 shall remain unchanged.
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC
No. 44/2006
Memo No.
50176/50976/SMI-259 dated
8.8.2006
Sub: Release of temporary tubewell connections during the paddy season of
2006.
Instructions
were issued for release of temporary tubewell connections during the paddy
season of 2006 vide CC No. 26/2006 dated 2.6.2006 . The para Viii of this
circular reads as under:-
" The service cable length of connection shall normally be
limited to 100 Mtrs.. However in hardship cases the length of service cable may
go upto a miximum of 110 Mtrs".
It has come to the notice of this office that the above clause is
being misused by adopting pick& choose policy in respect of 'hardship cases' .
The matter has been considered & it has been decided that
temporary tubewell connection shall be allowed with maximum service cable upto 110 Mtrs.
All other terms & conditions of CC No. 26/2006 dated. 2.6.2006
shall remain unchanged.
Dy.C.E./Sale
For Chief
Engineer/Comml.
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C
43/2006
Memo
No.49219/50019/SSM-414/TW-07-07
Dated
4.8.2006
Sub: - Tubewell Policy for the year 2006-07.
Keeping in
view pending test reports as on 31.3.06 as per the data / information received
from Chief Engineers/DS, the policy for release of new AP T/W connections during
the year 2006-07 has been considered and it has been decided as under :-
i) Target for release of 40,000 No. new AP tubewell connections during the
year 2006-07 has been fixed which
shall cover the test reports received upto date both for General Category and
Priority Categories. Adequate funds should be got allocated for release of these
connections so that the material for release of connections is provided by the
Board.
ii) Based on the zone wise position of the pending test reports as on
31.3.06,the allocation for each zone has been fixed as under:-
SR.No. |
Zone |
No. of
connections allocated |
1. |
West |
15300 |
2. |
South |
11000 |
3. |
North |
4300 |
4. |
Central |
5500 |
5. |
Border |
3900 |
| |
Total |
40,000 |
The
quarterly progress report for the release of tubewell connections shall be sent
by CE/DS concerned to CE/Commercial so as to monitor the progress achieved.
iii) As per data available, there are 39,589 No. pending Test reports as on
31.3.06 against which tubewell connections are yet to be released. Keeping in
view the target of 40,000 No fixed for the release of. new AP tubewell
connection during the year 2006-07,only these 39,589 pending test reports would
be covered for release of tubewell connections. Besides these test reports, the
test reports to be received against priority categories during the year shall
also be covered.
I}}}iv) }}Although cut-off date for issue of demand
notice under general category is 31.3.91 but keeping in view the pending test
reports it has been decided that demand notice(s) against applications
registered under general category from 1.4.90 to 31.3.91, shall not be issued
upto 31.12.06 after which this will be reviewed & necessary instructions to
allow issue of Demand Notice(s) for application registered from 1.4.90 to
31.3.91, if feasible, will be issued. However Demand Notice(s) for the applications registered upto 31.3.90 will continue to
be released as per instruction already inforce.
The ban imposed on issue of fresh demand notices w.e.f. 12.4.02 shall
continue except for applications registered upto 31.3.1990 under General
category besides priority cases allowed under Chairman's discretionary quota
(five percent), Ex-serviceman's priority & Kandi area priority.
v) The issue of
demand notices by the Sub Divisions shall be
regulated by Dy.CE/SE/DS, who shall, keeping in view the availability of
material, decide the number of demand notices to be issued by respective Sub
Division on quarterly basis in such a way that Sub Divisions will be in position
to release the connection(s) within three months from the date of compliance of
demand notice(s) by the prospective consumers.
vi) All out efforts need to be made by the
field officers to clear the applications registered upto 31.3.88 for which
strict compliance of the following instructions already issued vide CC.25/2006
dt. 2.6.06 amd as amended vide CC No. 42/06 dated 3.8.06 be ensured by field
officers :-
a) Issue
of material for release of new AP tubewell connections will be allowed only in
respect of test reports received against applications registered upto 31.3.88 in
the order of seniority based on the date of registration of the application.
b) No material shall be issued by Stores Organization for the release of
tubewell connections under general category against applications
registered after 31.3.1988 till the back log of applications registered upto
31.3.88 is cleared in all the zones and revised instructions will be issued
thereafter .
vii) As per procedure presently being followed for release of T/W connection,
separate seniority queues such as Chairman priority ,Ex-serviceman priority,
Kandi Area priority ,HT/LT seniority queues, own T/F seniority etc.are maintained at Sub Division level. SDO incharge should monitor at
his personal level that the connections in all the seniority queues are released
side by side. The following
procedure shall be followed for the release of AP tubewell connections/issuance
of material by the field officsers :-
(a) Chairman Priority connection shall have over riding priority over all
other categories.
(b) For other categories ,the roster for
release of connections/issue of material shall
be followed as under:-
i) 1st – General
Category.
i) 2nd _ General
Category.
ii) 3rd _ General Category
iii) 4 th _ Ex-servicemen Priority
iv) 5 th _ Kandi Area Priority.
v) 6th _ Own Transformer Priority.
vi) 7th _ General Category and so on.
If
test report against any priority category is not pending ,then slot for that
priority category will go to general
category. For example in a sub-division if no test report under Ex-servicemen
priority is pending, then 4th slot in the roster will also go to General
Category.
viii) As per instruction issued vide CC 13/2006 dated 17.3.06, the new AP T/W
connection shall continue to be released on LT supply upto 30.9.2006.
ix
) Voltage
Regulation of 11KV feeder may not be a constraint for issue of demand notice to
such prospective consumers, who are otherwise eligible for issue of demand
notice. In such cases, an undertaking/affidavit that AP connection under the
present system constraints is acceptable shall be obtained from the prospective
consumer as per the existing instructions.
x) CE/MM & CE/Workshop shall assess the requirement of material and take
necessary steps to ensure timely procurement of material required for release of
40,000 Nos. new AP tubewell connections during the year 2006-07 keeping in view
the decision taken by WTMs on 14.6.06 to release all new AP tubewell connections under HVDS w.e.f.
1.10.2006.
xi) The
status of pending test reports,demand notices may be displayed on the Notices Board of concerned operation Sub-Division with regard to release
of AP connection during the year 2006-07.
All other
terms and conditions for release of tubewell connection shall remain unchanged.
Dy.C.E./Sales,
For Chief
Enginee
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C:C:No.42/06
Memo No. 42248/49059 /SSM-414 Dated:
03.08.06
Sub: - Release of tubewell connection under General Category.
Instructions
were issued vide CC 25/2006 dated. 2.6.2006 that no materal shall be issued by
store organisation under general category against applications registered after
31.3.88 till the backlog of applications registered upto 31.3.88 is cleared in
all the zones of PSEB. Para-III of the above circular provides as under :-
"The
works already in hand for whilch sufficient material stand issued before
31.5.2006 shall be completed & may not be withheld on account of above
instructions . However, where only Poles and fittings /stay set etc. have been
issued,no further material be issued".
The above relaxation was given
with a view that the genuine cases where bulk of material stood already issued/given may not be unnecessary
withheld. It has however been observed that
tubewell applicants registered after
31.3.88 are putting all sorts of pressures to get the material released under provision of above para with the result that most of the tubewell
connections being released are for applications registered after 31.3.88. This
has defeated the very purpose of nstructions
issued vide CC-25/06 dt. 2.6.06. Accordingly, it has been decided to delete Para III of CC-25/06 dt. 2.6.06 with immediate effect.
All other terms & conditions of CC 25/06 dated 2.6.2006 shall remain
unchanged
Dy.C.E./Sales,
For Chief
Engineer/Comml.,
PSEB,
Patiala.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC
No.41/2006
Memo No. 2170/2970 Dated: 1.8.2006
Sub: Consumer Complaint Handling Procedure- Constitution of Dispute Settlement
Committees.
In continuation of instructions regarding 'Consumer Complaint Handling
Procedure' to be followed with effect from 1.8.2006 issued vide CC.No.40/2006
dated 29.7.2006, it is clarified that various Dispute Settlement Committees of
PSEB shall stand reconstituted w.e.f. 1.8.2006 as under:-
A) Zonel Level Dispute Settlement Committees (ZLDSCs)
1 |
Chairman |
: |
Engineer-in-Chief/CE/DS
of concerned Zone |
2 |
Member
from Accounts Wing |
: |
a) |
Chief
Auditor- Central,South &West Zones |
: |
b) |
CAO Revenue
- North & Border Zones |
3 |
Member
from Commercial Wing |
: |
a) |
Dy.CE/Dir.Sales-I
- Central Zone |
b) |
Director/Sales-II
- North & Border Zones |
c) |
Director/Billing - South & West
Zones |
4 |
Nominated
Members |
: |
Representatives
of the Industry for the respective zone as per CC No.4/2005 dated 14.1.2005 |
B) Circle Level Dispute Settlement Committees (CLDSCs)
1 |
Chairman |
: |
Dy.CE/
SE/DS of concerned Circle |
2 |
Member
from Accounts Wing |
: |
Dy.C.A.
of concerned Zone under which
the Circle falls |
3 |
Member
from Commercial Wing |
: |
Dy.Director/Sales
dealing with the concerned Circle |
4 |
Nominated
Member |
: |
Representative
of the Industry for the respective zone as per CC No.4/2005 dated 14.1.2005 |
C) Divisional
Level Dispute Settlement Committees (DLDSCs)
1 |
Chairman |
: |
Addl.
SE/Sr.Xen/DS of concerned Zone |
2 |
Member
from Accounts Wing |
: |
Accounts
Officer/Field of concerned Circle under which the Division falls. |
3 |
Member |
: |
Xen/AEE./AE
to be designated by concerned Dy.CE/SE/DS from within the Circle. |
All other terms and conditions of CC No.40/2006 dated 29.7.06 shall
remain unchanged.
Dy.C.E./Sales,
For Chief
Engineer/Comml.,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C:C:No. 40/2006
Memo No. 1242/2042 / SSM-118 Dated: 29.7.2006
Sub: - Consumer Complaint Handling Procedure.
In order to provide an inexpensive,expeditious and efficacious mechanisum to resolve the
differences and disputes, the Board had constituted a number of committees at
different levels to settle the
differences / disputes arising between the Board and the consumers. The exising set up of the various Dispute Settlement Committees as
constituted by the Board is as per ESR-No.142 and as amended by instructions
issued vide CC.No.4/05 dated 14.1.2005
and 39/05 dated 7.6.2005.
2. In terms of the provisions of Regulation-5(2) of the "PSERC (Forum
& Ombudsman) Regulations,.2005", PSERC vide its order dated June
26,2006 has approved the ' Consumer Complaint Handling Procedure' vide its letter No. 3385
dated 28.6.06 (copy enclosed) & have directed that this system shall be effective from 1.8.2006. The said procedure is self explanatory and needs no
elaboration.
3. It should be ensured that the
new system is set in place well in time and made functional from the date
specified by the Commission i.e. 1.8.2006.
The salient features of the 'Consumer Complaint Handling Procedure' as
approved by the PSERC are as under:-
i) Nature of Complaints
Consumer
complaints shall pertain to:
· Billing
· Metering
· Interruption/failure of power supply
· Voltage variations
· Load shedding/scheduled outages
· Disconnection/Reconnection
· Any other matter concerning supply of electricity
ii) Constitution of various Dispute Settlement Committees has been
mentioned in para-4 of the enclosure. As required under para-4 (2) and para
–4(3) of 'Consumer Complaint Handling Procedure', the Presenting Officer and Nodal Officer shall be as under:-
| |
Dispute
Settlement Committee- |
Presenting
Officer |
Nodal Officer |
Financial
Limit |
a) |
Zonal
Level Dispute Settlement Committee-(ZLDSC) |
SE/Dy.CE/DS
of the concerned Circle. |
SE/Dy.CE/HQ
Circle of the concerned |
All
cases above
Rs.2
lacs in each
case. |
b) |
Circle
Level Dispute Settlement Committee
(CLDSC) |
Sr.Xen/
Addl.SE/ DS of the concerned Circle |
Sr.Xen/Addl.
SE/Tech.of the concerned Circle |
All
cases above
Rs.50,000/-
and
upto
Rs.2 lacs in each case. |
c) |
Divisional
Level Dispute Settlement Committee-(DLDSC) |
Xen/AEE/AE/DS
of the concerned Sub-division |
Divisional
Supdt.of the concerned Division |
All
cases upto
Rs.50,000/-
in
each case. |
iii) The procedure for redressal of complaint as per para –6 of 'Consumer 'Complaint Handling Procedure', shall be strictly followed.
However, as far as para –6(8) is concerned, it is decided as under:-
When unanimity
is not reached while disposing of the disputed case by the above Dispute
Settlement Committee, the majority decision will be applicable. However, the
minutes to be recorded shall be self speaking and views of dissenting Member(s)
should be indicated alongwith the operating part of the decision specifically.
Copy of decision in each case shall be sent by Chairperson of DSC concerned to CE/Commercial without exception.
As per para-6(12) of 'Consumer Complaint Handling Procedure' the
Chairperson of DSC is competent to fix the amount to be deposited before
consideration of the case by the Committee. In case the consumer is unable to
make the part payment of 20% ,the chair person will record the specific reasons
for fixing the amount to be got deposited less than the part payment of 20%.
iv) Regarding para-6(14) of 'Consumer Complaint Handling Procedure', it is
clarified that the Nodal Officer will maintain proper record of all the
complaints received as disposed off on
behalf of the DSC.
i) The 'Consumer Complaint Handling Procedure', shall come into effect with effect from 1.8.2006
and all the existing complaints/appeals (all cases pending for review /appeal in
various DSCs / DSA) except those on matters pertaining to open access granted
under the Electricity Act,2003 and Sections 126,127,135, to 140,142,143,146,152
and 161 of the Act, before any authority previously constituted(i.e. DSCs / DSA) shall stand transferred to the jurisdiction of respective Dispute
Settlement Committees and Forum for Redressal of the Grievances, as the case may
be. All the previously constituted committees shall cease to exist with
effect from 31.7.2006.
ii) The field officers will :-
a) give wide publicity to the existence of the 'Consumer Complaint
Handling Procedure' by periodical press release, display on notice boards in the
distribution sub-divisions or at the Complaint centres/Bill collection
centres,web site of PSEB and such other means to make the public aware of the procedure;
b) make available an updated copy of the 'Consumer Complaint Handling
Procedure' ,as revised from time to time for inspection by members of the public
during normal working hours:and
c) Provide an updated copy of the aforesaid procedure revised from
time to time to the consumers and any other person who requests for it at a
price of Rs. 50/- per copy.
vii) Consumer's
right to approach the Forum.
A complainant aggrieved due to non-redressal of his complaint under
the 'Consumer Complaint Handling Procedure', may approach the Forum established
by the Board vide CC.27/06
dt.6.6.2006 under as sub-section (5) of Section 42 of the Act read with "
PSERC (Forum & Ombudsman) Regulations, 2005."
DA/as
above.
Dy.C.E./Sales,
For Chief
Engineer/Comml.,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 39/2006
Memo No. 47098/47898
Dated
: 27.7.2..06
Sub:- Regulation on installation and
operation of Meters.
GOI/CEA has notified vide notification NO. 502/70/CEA/PD&D dt.
17.3.2006 on the above subject under section 55(A), clause 73(e) read with
section 177(2)(c) of Electricity Act-2003 regarding regulating the installation
and operation of meters. These
regulations have come into force w.e.f. 17.3.2006. The special features of the regulations as well as action required as per these regulations and
responsibility center as per provisions and further responsibility of various
HODs in PSEB has also been
shown in annotated form. These instructions and the tabulation are enclosed for
further necessary action.
DA/As above,
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 38/2006
Memo
No. 44937/45737 /SMI-260
Dated: 25.7.06
Sub: Construction of unauthorized colonies-Release of Electricity Connection.
There are reports from the field
officers that mushroom growth of illegal /unauthorized construction of
Houses/Colonies is taking place below 66 KV and 11 KV lines of PSEB and in some
cases the clearance of 66 KV lines has been reduced to 2-
3 feet
from the unauthorized constructed buildings,which is violation of Indian
Electricity Act and is a threat to human lives.
In view of above ,the matter has been considered and it has been decided
that in no case any electricity connection shall be released to a prospective
consumer(s) where the power line(s) are passing over his (their) plots, till
such time, the lines are got shifted by the individual(s) or the Housing Society
etc.at his (their) cost.
Strict compliance of the above instructions be ensured by the field
officers.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 37/2006
Memo
No.43430/44230 / SSM-460
Dated: 18.7.2006
Sub: T & D Loss Reduction and Improvement in consumer service-Instructions
thereof.
T&D loss
reduction has been an area of major concern for last couple of years. Inspite of our best efforts coupled with enhanced inputs under
APDRP, the T& D losses are still in the range of 25% since last 2-3 years
.Even the PSERC has effected reduction in ARR for not achieving the targets of
reduction in T&D losses. With a view to take concrete steps to achieve
desired results in the coming years, the Board has approved a Roadmap for
Reduction in T& D losses. Accordingly following decisions have been taken.
1) Release of New AP Connection :-
As per instructions already issued vide CC.No. 13/06 dt.17.3.06, it was
decided that all new AP tubewell connections shall continue to be released on LT
upto 30.9.06. This means that from 1.10.2006, all new AP tubewell connections
shall be released under HVDS only by providing individual small rating
distribution transformers for each connection on single pole structure. The
distribution transformer shall be procured and installed by PSEB as near to the
tubewell bore- site as possible. In no case length of LT overhead cable
shall exceed
10 metres
.
For
release of individual connection, the distribution transformer shall be provided
as under: -
Sr.No. |
Load |
Capacity of Dist. T/F |
i) |
3 BHP/5 BHP |
6.3
KVA |
ii) |
7.5 BHP/10 BHP |
10
KVA |
iii) |
12.5 BHP/15 BHP |
16
KVA |
iv) |
20 BHP/25 BHP |
25
KVA |
The release of load less than 5 BHP shall, however, be discouraged &
will be released only with the approval of concerned Dy.CE/SE/DS recording
reasons for the same .
2. Release of New MS connection:-
As per schedule S II.2 of the Schedule of Tariff the supply voltage for
release of MS connection having connected load ranging from 21 KW to 100 KW is 3
phase,400 volts or 11KV at supplier's option. It has now been decided that w.e.f
1.10.06 onwards,all new MS connections having connected load above 50 KW shall
be released only by providing independent 63/100/200 KVA distribution
Transformer depending upon the load to be released . The metering will ,however, be done on LT side with
meter and CT/PT chamber on the Transformer H-Pole itself. If T/F capacity
permits,one or two more connections may be given from the same T/F but all
meters shall be on H-Pole only.
For load ranging from 21 KW to 50 KW, the connection shall be released
with LT metering by installing independent 25 KVA /63 KVA T/F, with zero LT in
the above manner . The meter shall be installed in MCB or Pillar Box on the pole /under the distribution Transformer . Where installation of new transformer is not possible due to locational
reasons /site constraints and the connection has to be from a common transformer ,the
metering equipment of all consumers on the transformer shall be installed on
transformer H-pole in MCB / CT /PT chamber or
in the pillar box as the case may be.
3. Release of new SP / NRS / DS Connection:-
As per schedule III.2
of Schedule of Tariff for SP, the supply voltage for small industrial loads upto
20KW is 3 phase 400 volts or single phase 230 volts. As per schedule SV.2 of
Schedule of Tariff for NRS, the character of service provides supply voltage of
single phase 230 volts or 3 phase 400 volts. For loads upto 10 KW, supply is
given at single phase 230 volts, for loads above 10 KW and upto 100 KW, 3 phase
400 volts supply is given & for loads exceeding 100 KW, supply is given at
11KV.
In order to reduce T&D losses it has now been decided that wherever
supply is given at 230 volts or 400 volts, the meter shall be provided in the
Pillar Box or MCB on pole or outerwall of the premises as per site condition. In
no case meter shall be installed inside the consumer premises.
In all these categories of SP/NRS /DS, for loads ranging from 11KW to 50
KW (upto 20 KW in case of SP consumers), the connection shall be released with
LT metering in 3 phase category by providing independent T/F of 10/16 /25 /63KVA
or higher capacity with zero LT and meter shall be installed in MCB or pillar
box on the pole /under the distribution transformer. However more than one
connection can be given from the same T/F if the premises are nearby by
providing meters in pillar boxes or in MCB /CT Chambers on poles.
All DS /NRS connection with loads ranging from 51 KW to 100 KW shall be
released at 11 KV only with LT metering by providing independent 63 /100/200 KVA
distribution transformers. DS/NRS loads above 100 KW shall continue to be
released as per existing instructions as per Schedule of Tariff SV and SVI, at
11 KV supply voltage as per discretion of the Board.
4. System Improvement Works & Deposit Work
Estimates for all S.I. and deposit works shall be prepared/sanctioned as
per guidelines in para 1 to 3 above with the objective of zero LT and meter in
Pillar Box /MCB on Pole /MCB on outer wall of consumer.
5. Loading of Distribution Transformers:-
It shall be ensured by
the field officers that loading of distribution transformer is upto 80% of the
transformer capacity. The strict compliance of these instructions shall be
ensured even in case of release of GSC connections.
6. HVDS in GSC/ISC:
In urban areas, residential premises in Posh/Planned Colonies having high load of AC, Heaters/Geysers and other gadgets, incidence of theft in
such premises is very high and loss of revenue is also substantial. It is,
therefore, decided that transformers to be spared from AP under HVDS should be
installed in such colonies to cater to a cluster of 4/5 to 8/10 houses depending
on load and meters should be installed in Pillar-Boxes/MCBS. This will ensure
zero LT and no commercial loss /theft. Similar action shall be taken in the case
of commercial premises in planned shopping centres/malls etc. and SP/MS
connections in industrial estates and other areas also. In nutshell, all DS/NRS/SP/MS
connections shall be released in future on HVDS with least /zero LT .Further
bare conductor overhead LT lines which allow direct hooking shall be avoided.
5. D.T. METERING.
As decided with PSERC,
there is no necessity of providing meters on agricultural load transformers.
Therefore, DT meters may be provided in the first phase on all the urban
Distribution Transformers for effective energy accounting and audit and in the
second phase the DT meters shall be installed on Distribution Transformers
catering to GSC /ISC loads in rural areas.
The above instructions shall
be applicable with effect from 1.10.2006 so that the material is arranged by
that time. However, action regarding installation of meters outside consumer
premises shall be taken immediately.
Sd/-
Dy.CE/Sales,for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 36/2006
Memo
No. 43392/44192/Gen.condition/Tariff
Dated : 14.7.06
Sub:- General Conditions of Tariff and
Schedule of Tariff.
Punjab
State
Electricity Regulatory Commission have framed revised general conditions of
tariff and Schedule of Tariff. Which
have already been supplied to all CEs/Op. vide this office memo No. 18294/98 dt.
5.4.06 and to all SEs/op. vide this
office memo No. 20280/99 dt. 13.4.06. Please
find enclosed the copy of the same for taking further necessary action please.
DA/As above
6-46 pages.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 35/2006
Memo No. 42262/43062/SSM-315
Dated: 12.7.06
Sub: Payment /Recovery of interest on disputed amount.
Continuation of CC 61/05 dated.7.9.2005 .
It has been decided that the existing rate of 9% per annum for payment
/recovery of interest on the disputed amount shall remain operative during the
year 2006-07.
Sd/-
Dy.CE/Sales,for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC
No:34/2006
Memo
No.40965/41765/SR 134.5
Dated:6.7.2006
Subject: POWERS OF THE OFFICERS OF THE BOARD TO ENTER CONSUMER PREMISES FOR
CHECKING/ INSPECTION UNDER SECTION 135 (2) OF e.a. - 2003 - Assessment of
unauthorized use of Electricity, Assessing Officers, uNDER sECTION 126 OF e.a.
– 2003, APPELLATE AUTHORITY UNDER SECTION 127 OF THE EA -2003 and COMPOUNDING OF CHARGES IN CASE OF Theft of Electricity Under Section 152
of EA-2003.
Government
of
Punjab
, Department of Power( Energy Branch) has issued following notifications on the
subject:-
1. No. 1/13/04-EB (PR)/23 dated 10 January,2005:
This is regarding designating the PSEB
Officers for the implementation of provisions Under Section 135(2) of the
Electricity Act-
2003 in
their respective power distribution areas. According to this notification Commercial Circular No.24/05 dated
12.4.2005 was issued, as per which, JEs were not authorized to enter the consumer premises for checking/inspecting the
same. Matter was referred to
Secretary/Power, Govt. of Punjab vide memo No. 76 dated 7.6.2005 to allow JEs/AAEs
also to enter the premises of Domestic, NRS, AP/SP and Bulk Supply connections
upto 20 KW but till date the Pb.Govt.
has not accepted this proposal.
As
theft of energy in this category of consumers had increased, Board had to issue
CC 57/05 dated 31.8.2005 enjoining upon all PSEB officials, JEs, MRs and BDs to
intimate & report the case of theft of energy taking place in the Domestic
premises. Further vide CC 60/2005
dated 6.9.2005, JEs/AAEs were again
authorized to check the consumer premises as per practice prior to the issue of
CC 24/205 dated 12.4.2005. Govt. of
Punjab
is yet to approve the instructions issued vide Commercial Circular No. 60/05. Pending approval of the Govt. the checking of various categories of
consumers should continue as per the practice before issue of CC 24/2005 i.e.
JEs /AAEs are authorized to check the consumer premises of Domestic/NRS/SP
connections as per the schedule (Page-53) for Conditions of Supply (Copy
enclosed at Annex-I). E.S.R.
134.5 should be treated as amended to this extent subject to approval of Govt.
of Punjab.
2. 1/60/03-EB(PR)/1186 dated 27.12.2004:
The State Govt. has
authorized the following officers of the Board to make assessment of charges
payable by the LT & HT consumers in case they are found indulging in
unauthorized use of Electricity Under Section 126 of the Act.
| Category of consumers |
: |
Assessing Officers |
All HT consumers above 1 MW load |
: |
CEs of the Operation Wing of respective Distribution area |
All HT consumers upto 1 MW load |
: |
SE/Dy.CEs of Operation wing of the Distribution area.. |
All LT Industrial consumers |
: |
Sr.Executive Engineers/ Addl.SEs of Operation wing of the
Distribution Area |
All other LT consumers |
: |
Assistant Engineer/ Assistant Executive Engineers/
Executive Engineers of Operation wing of the Distribution Area. |
Note:- Unauthorized use of electricity means
the usage of electricity:-
(i) by any artificial
means ; or
(ii) by a means not
authorized by the concerned person or authority or licensee; or
(iii) through a
tampered meter; or
(iv) for the purpose
other than for which the usage of electricity was authorized. The cases of prejudicial use of supply, re-sale of energy &
malpractices referred to in SR-137 (Copy enclosed at Annex-II)
shall be covered under unauthorized use of electricity and dealt as per
provisions of Section 126 of E.A.2003.
It
is clarified here that unauthorized extension in load is not covered under
misuse of electricity. It is
separately governed by provision of load surcharge given in Schedule of Tariff
circulated vide memo No.30078/30103 dated 1.6.06. Any dispute regarding levy of load surcharge shall be adjudicated by the
existing Dispute Settlement Committees. Similarly,
disputes other than those related to misuse of electricity shall also be
adjudicated by existing DSCs.
3. No.1/13/04-EB(PR) 161 dated 9.3.06:
The Pb. Govt. has authorized the following
officers of the State Govt.as Appellant Authority for the purpose of deciding
appeals Under Section 127 of the Electricity Act-2003 against the orders of the
Assessing Officers made Under Section 126 of the said Act.:-
Category
of consumers |
: |
Appellate
Authority |
For appeals by all HT consumers |
: |
Divisional Commissioners in whose jurisdiction the
concerned premises is located. |
For appeals by all LT industrial consumers |
: |
Addl. Deputy Commissioners (General) in whose jurisdiction
the concerned premises is located. |
For appeals by all other LT consumers |
: |
Sub Divisional Magistrates in whose jurisdiction the
concerned premises is located. |
The procedure for filing
appeal before the Appellate Authority is laid down in the PSERC notification
dated 7th March-2005 bearing No. PSERC Secy./Regu.14 dated 7.3.2005 (Copy enclosed for ready reference at Annex-III ).
4. No.1/27/05-EB(PR)/204 dated 22.3.06.
(A) The Govt. of Punjab has notified the following rates of compounding
charges in case theft of energy Under Section 152 of the Electricity Act-2003:-
i) |
Industrial
Services(SP & MS) |
= |
Rs.10,000/- per KW or part thereof of sanctioned load. |
ii) |
LS
(Gen. & Power Intensive) |
= |
Rs.10,000/- per KW or part thereof of sanctioned load
or
Rs.10,000/- per
KVA of Contract Demand whichever is higher |
iii) |
Commercial/NRS |
= |
Rs.5,000/- per KW or part thereof of sanctioned load. |
iv) |
Agriculture |
= |
Rs.2,000/- per BHP or part thereof of sanctioned load. |
v) |
Other Services (Domestic & Bulk Supply) |
= |
Rs.3,000/- per KW or part thereof of sanctioned load. |
(B) Further, the Govt. of Punjab has authorized the following officers of
PSEB to recover/collect the above said compounding charges from the
consumers/persons for the offence of Theft of Electricity:-
i)(a) |
All Domestic, Bulk Supply, Agriculture and Commercial
Connections. (LT & HT) |
= |
SE/Distribution of the respective areas |
(b) |
All Industrial SP connections. |
= |
SE/Distribution of the respective areas |
ii) |
All LS & MS industrial connections. |
= |
CE/Distribution of the respective areas |
(C) The compounding charges recovered from the consumers/persons will be
deposited on the same or the next working day by the concerned
Officers/authorities in the Account Head of Punjab Government given as under:-
" Major Head "0043- Taxes and Duties on Electricity."
5. Brief
instructions of Dos & Don'ts as
well as instructions containing summarized provisions of the E.A. 2003 regarding
theft & unauthorized use of electricity are enclosed as Annex-IV..
6.(I) The cases of the misuse of electricity for which no notice
has been issued to the consumer so far maybe processed as under:-
(i) The provisional
assessment order as per section 126 shall be served upon the consumer by the
assessing officer. After affording
reasonable opportunity of hearing
against the objections filed by him,
the assessing officer shall pass an order of the charges payable by the person
giving him seven days for representing against its provisional assessment order.
(ii) The consumer will
be at liberty to prefer the appeal with the appellate authority as mentioned in
Notification No.1/13/04-EB(PR) 161 dated 9.3.06.
(iii) If the consumer
fails to deposit the assessed amount or to prefer an appeal with the Appellate
Authority within a period of 30 days from the date of issue of assessment order,
then a 15 days notice U/s 56 of the Act may be issued to him for depositing the
charges as per the assessment order. After
the expiry of 15 days the connection may be disconnected if the charges of
electricity raised in the assessment order are not deposited.
6.(II) Where notice/Assessment order for deposit of charges of
electricity on account of misuse of charges has already been issued , in such
cases consumer is required to deposit the charges within 7days or represent
against the assessment order, failing which the provisional assessment order
shall be converted into the final order. However,
consumer will have the option to appeal against this order to the appellate authority mentioned in Notification
No.1/13/04-EB(PR) 161 dated 9.3.06 within 30 days of the assessment order.
6.(III) Cases of misuse of electricity which are pending before the
existing review authorities like DSCs/DSA/BLRC, such cases of misuse of
electricity which have not been decided yet
by the review authority upto the date of issue of the circular may be decided expeditiously. However,
the existing departmental review committees shall cease to entertain cases of
misuse of electricity with immediate effect from the date of issue of these
instructions.
7. The compliance of the above mentioned notifications should be
carried out in letter and spirit. Any
difficulty in the implementation of these instructions may be immediately
brought to the notice of this office through CEs/Operation.
The above notifications (Copies enclosed) are being brought to the notice
of all Distribution Officers.
Encl:As
above.
Sd/-
Chief Engineer/Comml.
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 33/2006
Memo
No. 40049/40849/SMI-259
Dated: 6.7.2006
Sub: Policy for regularization of temporary tubewell connections released during the Paddy Season of
2005.
Priority scheme for regularization of temporary tubewell connections
released during the paddy season of 2005 was introduced vide CC.No.9/06 dated
24.2.06 followed by some clarifications/amendments vide CC.No. 12/06 dated
17.3.06 and 15/06 dated 10.4.06. On the basis of report from the field officers
that applications for regularization of temporary tubewell connection against
which certain clarifications had been sought by them could not be registered for
want of clarifications, the scheme was made operative upto 31.5.06 vide CC.No.
19/06 dated 31.5.06. Further the
date for completion of work for regularization temporary tubewell connection was
also extended upto 30.6.06.
There is a feedback
now from the field officers that many farmers who became eligible after issue of
clarifications/relaxation by this
office but it was not known to them, are still requesting for registration of
their applications for regularization of temporary tubewell connection released
during the paddy season of 2005. The matter has been considered and it has been
decided that priority scheme for regularization of temporary tubewell connection
introduced vide CC.No. 9/06 dated 24.2.06 followed by subsequent amendments/
clarifications shall remain operative upto 31.7.06 i.e. the eligible applicants
can now submit their applications for regularization of temporary tubewell
connection upto 31.7.06. The date for completion of work for regularization of
temporary tubewell connection is also extended upto 30.9.06.
All other
applicable terms and conditions shall remain unchanged.
Sd/-
CE/Sales, for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
32/2006
Memo No.38083/38883
Dated : 27.6.06
Sub: Guidelines for refund to be given to SC domestic consumers on Account of
free electricity supply upto 200 units per month having a connected load of above 300 watts and upto 500 watts
w.e.f.1.9.2005.
Instructions were issued vide circular No. 11/2006 dated 1.3.2006 to give
free electricity supply upto 200 units per month to domestic consumers belonging
to SC category having sanctioned load upto 500 watts w.e.f. 1.9.2005. As the benefit of free electricity upto 200 units/month was to be given
w.e.f. 1.9.2005, instructions were issued vide CC 17/2006 dated 21.4.2006 as per which cash refund was allowed to SC Domestic consumers having load
upto 300 Watts on account of increase in free electricity from 50 units to 200
units/month w.e.f. 1.9.05 vide CC no. 17/2006 through a special drive in field
from 26.4.2006 to 30.4.2006. It was
indicated in CC 17/06 that
instruction for refund to SC-DS consumers with a connected load above 300
Watts and upto 500 watts who have paid their bills w.e.f. 1.9.05 shall be issued
separately. Instructions were subsequently issued to the field to identify all
the SC-DS consumers irrespective of their connected load. Out of these SC consumers identified by field offices and such lists supplied to
this office, the SC-DS consumers with connected load above 300 Watts and upto 500 Watts have been got identified by
Director/Billing from computer data and Circle wise CDs/hard copies of list of
such consumers indicating the amount to be refunded against each consumer have been prepared and copies were handed over to respective S.Es, during
meeting held at Patiala with Chairman on 12.6.2006
The cash refund to such DS
consumers with connected load above 300 Watts and upto 500 Watts for the period
1.9.2005 to 31.5.2006 is to be processed as under in respect of consumers who have already submitted required documents
i.e. S. C. Certificate etc. and those who have been identified as per lists prepared/circulated but have yet to submit the required documents:-
i) The refund would be allowed in cash to the consumers through an individual docket voucher in the sub division under
the direct supervision of Sub Divisional incharge as per the list already
supplied by M/s DOEACC, Chandigarh. The docket vouchers would be prepared well
in advance as per lists and authentications by Sub Divisional incharge. The
refund would be allowed from 1.7.06 to 31.7.06 in the office of SDO for which
vide publicity will be made through press/electronic media, panchayats,
announcements in gurudwara/mandirs and by muniadi and also through City cables
in City/Urban areas. An advertisement to this effect is also being given
separately in the vernacular/other news papers.
ii) For identification of the payee,
the consumer shall bring the bill-cum-receipt for the last payment made in
respect of his electricity bill/voter identify card/any other identification.
The identification of the consumer shall be made by the concerned SDO on the
docket voucher.
iii) The bill-cum-receipt if produced
by the consumer shall be pasted at the back of the docket voucher and refund
allowed in cash after obtaining signature/thumb impression of the claimant.
However, if the consumer is not ready to part with the original receipt, a
photocopy of the same duly attested by the SDO/RA shall be retained/pasted at
the back of the docket voucher.
iv) The list of all the SC Domestic
consumers eligible for refund showing the amount due to each, would also be
displayed on the notice board of the
Sub Division for ensuring transparency and disbursement of correct amount to the
claimants.
v) The status with regard to the
refunds would be reviewed after 31.7.06. The payment to left out cases shall,
however continue to be made after 31.7.06 also.
vi) Those SC consumers with
sanctioned load above 300 Watts and upto 500 Watts (though identified but
documents not given) who come up with the statutory documents now and have
submitted the same shall also be allowed refund as per the above pattern
mentioned in
Para-
(i to v) w.e.f. 1.9.2005. It is made
clear that under no circumstances refund shall be allowed merely on the basis of
identification as per list unless
the required documents have been/are submitted by such consumers.
vii) After the refunds have been
allowed, account wise payment made would be communicated to our Computer Service Centres
in the Advice No. 76 after making entries in Sundry charges Allowance
Register so as to adjust the entries of negative bills by M/s DOEACC. Proper classification of SOP and ED however may be made in
the accounts of the Sub Division accordingly for the above refunds.
It shall be ensured that the
defaulting amount standing against any consumer is adjusted before allowing the
refund.
The refunds for the period after
31.5.2006 shall be afforded directly by the Computer Service Centres of PSEB to all the consumers
whose requisite advice have been sent by the field offices. All the field officers are instructed that they should invariably send
the requisite advice duly filled in to the concerned Computer Service Centres.
The instructions contained in
accounts circular No.10 of 2006 may also be kept in view,
The above instructions may be
conveyed down the line immediately for strict compliance of the instructions by
the Sub Divisional Officers. The Addl. S.E/Sr.Xen/Op. would personally monitor
the day-to-day progress achieved in this regard.
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
Endst
No. 38884 Dated: 27.6.06
CC No. 31/2006
Memo No. 35251/36051 / SMI-259
Dated: 15.6.06
Sub: Release of tubewell connections during the paddy season of 2006.
Instructions regarding release of temporary tubewell connections
during the paddy season of 2006 were issued vide CC.No. No.26/2006 dated 2.6.06.
Further instructions were issued vide CC No. 28/06 dated 7.6.2006 that no
temporary tubewell connection with motor capacity less than 5 BHP will be
allowed except in Bet Area.
On the basis of feedback
from the field officers during the review meeting taken by Chairman PSEB on
dated 12.6.06, the matter has been considered and it has been decided that that temporary tubewell connections with motor of less than 5 BHP capacity will be allowed in the District Gurdaspur also except the area under Ghuman Sub Division of Qudian Division of PSEB.
All
other terms & conditions of CC NO. 26/2006 dated 2.6.2006 shall remain
unchanged.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.30/2006
Memo
No. 34934/35134 /
Dated:
15.6.06
[
SUB: Introduction of token system at the Cash Collection Centres of PSEB.
The hardships/inconvenience caused to the consumers to deposit their
bills has been engaging the attention of Board for some time. Introduction of
bill payment to machines, payment of bills through Post offices/banks are some
of the steps taken in this direction. To further mitigate the problems of
consumers who have to stand in long queues for hours together for deposit of
their electricity bills at PSEB's Cash Collection Centres , the matter has been
considered & it has been decided to introduce a Token system at all the Cash
Collection Centres of PSEB as under:-
i) As & when a consumer comes to
deposit the Bill(s), he/she shall be issued a token bearing a serial number and
his payment shall be accepted when
his/her turn comes according to the serial number of the token allotted.
ii) An electronic display system of
the type installed at various Fast Food Centres shall be installed at the Cash Collecting Centre which will display the token no.of the consumer who is required to be
called for deposit of bill
The above system
will help the consumers to wait anywhere at a convenient place & come at the
counter when their turn come for deposit of bill(s) & thus avoid
inconvenience to the consumers.
iii) A notice regarding above procedure
shall be displayed at the Cash Collection Centres for the information of the
consumers.
All the field officers
are requested to ensure implementation of above instructions at the earliest
possible.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 29/2006
Memo
No.34965 / 35765/ ED Loose
Dated :9/6/2006
Sub: Levy of electricity Duty.
The Government of Punjab, in exercise of powers conferred by section 12
of the Punjab Electricity (Duty) Act, 2005 and all other powers enabling it on
this behalf vide Notification No.
13/18/05-PES/15895 has exempted the captive generating plant plant owners from
levy of electricity duty subject to the conditions mentioned below:-
a) Any
person, who owns and holds not less than twenty six per cent of the ownership of
a captive generating plant.
b) consumes
electricity for his own use not less than fifty one percent of the aggregate
electricity, generated in such plant, determined on an annual basis by the
competent authority. Provided that the exemption will be available only on the
electricity, generated from the captive power plant and consumed for captive
use.
Note:
The term “captive use” shall have the same meaning as has been assigned to
it in the Electricity Rules, 2005, framed by the Central Govt. under the
Electricity Act, 2003.
You are requested to take action accordingly and also ensure vide publicity for information of general public and all CPP owners may
be informed appropriately.
Sd/
Director/Sales-II
For
CE/Commercial,
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 28/2006
Memo
No.33954/34754/SMI-259
Dated: 7.6.2006
SUB: Release of tubewell connections during the paddy season of 2006.
Instructions
regarding release of temporary tubewell connections during the paddy season of
2006 were issued vide CC No. 26/2006 dated 2.6.06. some clarifications have been sought by the field officers which are
given as under:-
1. Clarifications have been sought by the field officers whether loading
conditions of the 1 KV feeders & Grid Sub-Stations are to be considered or
not for release of temporary tubewell connections.
The matter has been considered & it has been decided that temporary
tubewell connection shall not be released from any 11 KV feeder or Grid
Sub-station which is over loaded. The
decision regarding which 11 KV feeders/ Grid Sub-stations are over loaded, from
which temporary tubewell connections can not be released, shall be taken by
concerned Dy.CE/SE/DS & list of such 11 KV feeders/Grid Sub-stations shall
be prominently displayed in the Operation Divisions/Sub Divisions. The earnest money of the applicants who have applied for temporary
tubewell connections from such 11 KV feeders/grid sub-stations may be refunded.
2. It has been observed in the past that some applicants who actually
require to install 5 BHP tubewell connections based on water table, apply for 3
BHP tubewell connection but unauthorizedly install
higher capacity motor thus depriving the Board of charges of Rs.1,500/- per BHP
for the excess load besides putting hidden load on the system.
It has therefore been
decided that no applicant shall be allowed temporary tubewell connection with
motor capacity less than 5 BHP except in Bet Area. The applicants who have applied for 3 BHP connections and are not from
Bet Area should be informed immediately to deposit charges accordingly.
All other terms & conditions of CC No.26/2006 dated 2.6.2006 shall
remain unchanged.
Sd/-
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 27/2006
Memo
No.33019/33819/SSM-118
Dated:6.6.2006
SUB: ESTABLISHMENT OF FORUM FOR REDRESSAL OF GRIEVANCES OF THE CONSUMERS.
PSERC
issued notification No.19 on 17.8.05 enjoining upon PSEB to constitute a 'FORUM'
FOR REDRESSAL OF GRIEVANCES OF THE CONSUMERS under Section-42 (5) of the
Electricity Act-2003 called PSERC (Forum & Ombudsman) Regulation 2005. The composition of the FORUM as per clause 3 of the PSERC Notification
shall be as under:-
i) Chairperson of
the Forum shall be an Electrical Engineer with experience in distribution of
electricity, not below the rank of a Chief Engineer.
ii) One Member shall be an officer from Finance and Accounts cadre,
preferably having experience in revenue matters, not below the rank of a Chief
Accounts Officer or of equivalent status.
iii) One Member shall
be an officer of the level of a Superintending Engineer having experience in
commercial matters.
Notes:-
(i) The Chairperson & Members of the FORUM shall hold office ordinarily
for a period of two years from the date of appointment/nomination to the Forum.
No Member of the Forum shall hold office as such after he has retired from the
service of the licensee.
(ii) The licensee shall ensure that the posts of the members of the Forum are
not kept vacant for more than one month.
(iii) The licensee shall appoint/designate one of its officers not lower than
Grade-II officer as Full Time Secretary to the Forum and shall also provide
required supporting staff and office accommodation etc. for functioning of the
Forum.
2. The Board accordingly considered the matter in its 7/06 meeting held on
10.5.2006 and decided to establish 'FORUM' for the redressal of the grievances
of the consumers keeping the internal dispute settlement mechanism of PSEB
including DSA intact as under:-
(i) |
Chairman
of the 'FORUM' |
: |
Chief
Engineer/DSA shall hold the charge in addition to the charge under DSA |
(ii) |
Member
of the 'FORUM' with experience in revenue matters |
: |
CAO/DSA
shall hold the charge in addition to the charge under DSA. |
(iii) |
Member
of the 'FORUM' with experience in Sales matters |
: |
Dy.CE/SE/DSA
shall hold the charge in addition to the charge under DSA. |
(iv) |
Secretary
of the 'FORUM' |
: |
An
officer of the rank of Dy.Director shall hold the charge from the existing
strength of staff working under Chief Engineer/DSA. |
3. The expenditure
of the forum will be considered and allowed as a pass through expense by the
commission at the time of working revenue requirement of the Board.
4. Chairman, PSEB shall appoint/nominate the chairperson and members of the
'FORUM' from amongst the PSEB officers in accordance with the PSERC Regulation
19.3
a. The Chairperson
and Members shall hold office ordinarily for a period of two years from the date
of appointment/ nomination to the Forum. No
member shall hold office as such after he has retired from the service of the
Licensee/Board. Reg.19.3.4
b. The post of the
Members of the Forum shall not be kept vacant for more than one month. If the licensee/Board is unable to fill up the post(s) within a period of
one month, the commission may, at
the request of the licensee/Board grant such additional time as it deems fit to
the licensee/Board for the purpose of filling of such vacancy. Reg.19.3.5
c. In case the
Chairperson of the Forum is unable to discharge the functions owing to absence,
illness or any other cause, the senior member shall discharge the functions of
the Chairperson until the day on which the Chairperson assumes office. Reg.19.3.8
d. All decisions of the Forum shall
be on the basis of majority of the member present and voting. Reg.19.3.9
e. The
quorum for Forum meeting shall be two and each member shall have one vote and in
case of equality of votes on any issue or resolution, the Chairperson or a
member discharging the functions of the Chairperson and presiding over the
meeting shall, in addition, have a casting vote. Reg.19.3.10
The Forum shall ordinarily have sittings at its headquarters (
Patiala
). Reg.19.3.11
(B) Jurisdiction of the Forum:
(i) The Forum shall entertain the complaints filed in writing by the
complainant with respect to the electricity services provided by the
distribution organization of the Board/Licensee if it fulfills the following
requirements:- Reg.19.5.1
b.
Reg.19.2.(e)An
unfair trade practice or a restrictive trade practice has been adopted by the
Board/Licensee in providing electricity services;
c. The electricity
services hired or availed of or agreed to be hired or availed of by the
complainant, suffers from defect or deficiency in any respect;
d. The
Board/Licensee has charged for electricity service mentioned in the complaint, a
price in excess of the price fixed by the Commission;
e. Electricity
services which are hazardous to life and safety when availed are being offered
for use to the public in contravention of the provisions of any law for the time
being in force or of any license;
f. Violation has
occurred of any law or licence requiring the Board/Licensee to display the
information in regard to the manner or effect of use of the electrical services;
or
g. Breach has
occurred of any obligation by the Board/Licensee which adversely affects any
consumer or which the Forum may consider appropriate to be treated as a
complaint.
ii) The Forum shall entertain only those complaints where the complainant has
approached the appropriate authority of the Board/Licensee as prescribed in the
Complaint Handling Procedure approved by the Commission from time to time and
either is not satisfied with the response of the Board/Licensee or there is no
response within the time prescribed therein or within reasonable time.
No complaint shall be
entertained unless it is filed before the Forum within 3 (three) months from the
date the consumer exhausted the remedy under the Complaint Handling Procedure or
when no action is taken by the authority prescribed in that procedure within the
period prescribed therein, from the expiry of such period as aforesaid,
whichever is earlier. However, the
Forum may entertain a complaint, which does not meet the aforesaid requirement
with reasons to be recorded in writing. Reg.19.5.2
iii) The Forum shall not entertain a complaint if it pertains to the same
subject matter for which any proceedings are pending before any court, authority
or any other Forum established by law or a decree, award or a final order has
already been passed by any competent Court, authority or Forum or is frivolous
or vexatious in nature. Reg.19.5.3
Reg.19.6.1(C) Filing of Grievances before the Forum:
(i) The Forum shall take up the various types of complaints/ grievances, may
be relating to the following issues, which are not related to open access
granted under the Act and Section 126, 127, 135 to 140, 142, 143, 146, 152 &
161:-
a) Billing of supplementary amount as a result of post audit.
b) Levy of voltage surcharge not levied in the first instance.
c) Wrong Billing.
d) application of wrong tariff.
e) Non payment of admissible rebates/incentives.
f) Delay in release of connection.
g) Delay in issue of first bill/subsequent bill.
h) Delay in rectification of energy bill.
i) Delay in replacement of defective/dead stop meters/ Metering
equipment.
j) Non-restoration of supply due to breakdown or even after
payment of dues.
k) Levy of clubbing charges either by way of differences of
tariff or high voltage surcharge from back date of 1.1.96 {Unfair trade practice
when charges for not more than 2 years are leviable as per Section 56(2) of E.A.-2003.}
l) Supply of low voltage beyond the limits permissible under
IER 1956, fluctuations in voltage etc. (Deficiency in service).
m) Accidents due to less clearances being not as per IER 1956
faulty lines etc.
n) Leakage of earth current and consequent accidents.
o) Inadequate grace period for deposit of energy bill.
p) With-holding information required by the consumer etc.etc.
Note:- The above list of complaints is not to be treated as final. There may be complaints which are not covered by the above list. Such complaints related to supply of electricity not mentioned above may
also be taken up by the Forum.
(ii) Every grievance must be submitted in writing by complainant(s) with
following details to the Forum:- Reg.19.6.2
(a) The name of the individual or the organization, complete postal address,
telephone number, fax number and the E-mail address, (if any), The name of
Board/Licensee Office i.e. Sub-Divn., Division or Circle Office to which the
grievance pertains.
(b) A full description of the matter, which is the source of grievance,
including copies of any relevant and supporting documents, if any.
(c) Relief prayed for.
(d) Statement that the matter is not pending before any other Court,
Authority or Forum.
(I) The complainant shall enclose a copy of response if any from the Board/Licensee. Reg.19.6.3
(ii) The Forum may seek additional information and details from the
complainant(s). Reg.19.6.4
(iii) The Forum may also accept
complaints through e-mails or web site subject to fulfillment of such
requirements as the Forum may consider appropriate. Reg.19.6.5
(D) Procedure for disposal of grievances by
the Forum:
(i) On receipt of the consumer grievance, the Secretary to the Forum shall
make an endorsement on the grievance subscribing his dated initials and shall
send an acknowledgement to the applicant within 7 days of its receipt. The secretary shall also be responsible to inform the complainant of the
status of his complaint in the Forum in case of inquiry by the complainant in
this regard. Reg.19.7
(ii) The consumer grievances received shall be registered and serially
numbered for each year e.g. C.G No.1/2005, 1/2006 and so on and copy of the
grievance shall be forwarded simultaneously to the concerned officer of the
Licensee/Board for redressal or to file objection, if any, in writing in case
the licensee/Board is not agreeable to the request of the complainant.
(iii) The
employee nominated/authorized in this regard by the Licensee/Board or the
employee named in the complaint shall furnish the parawise comments on the
grievance within 15 days from the date of receipt of the letter from the Forum,
failing which the Forum shall proceed on the basis of material available on
record.
(iv) The
Forum may also call for, any record of the Licensee/Board or from the
complainant relevant for examination and for disposal of the grievance and the
parties shall be under obligation to provide such information, document or
record as the Forum may call for. Where
a party fails to furnish such information, document or record and the Forum is
satisfied that the party in possession of the record is with-holding it
deliberately, it may draw an adverse inference.
(v) On receipt of the comments from the Licensee/Board or
otherwise and after conducting or having such inquiry or local inspection
conducted as the Forum may consider necessary, and after affording reasonable
opportunity of hearing to the parties, the Forum shall pass appropriate orders
for disposal of the grievance, as far as possible, within 60 days of filing the
complaint.
(vi) The proceedings and decisions of the Forum shall be recorded
& shall be supported by reason. The
order of the Forum shall be communicated to the complainant and Licensee/Board
in writing within 7 days. The
Licensee/Board shall comply with the orders of the Forum within 21 days from the
date of receipt of the order.
(vii) The Forum may, subject to Electricity Supply Code and
related matters Regulations made by the Commission in this regard, award such
compensation to the complainant(s), as it considers just and appropriate in the
circumstances of the case. The Forum
may issue such interim orders pending final disposal of the complaint, as it may
consider necessary. It may also
order for deposit of any Interim amount by the complainant with the
Licensee/Board.
(viii) Where the complainant or the Licensee/Board fails to appear
before the Forum on the date fixed for hearing on more than two occasions, the
Forum may decide the complaint ex-parte.
(ix) The forum may settle any complaint in terms of any agreement
reached between the parties at any stage of the proceedings before the Forum and
there shall be no right of representation before the Ombudsman against such
order
(x) The Forum may evolve procedure conforming to the principles of fair play
and justice for efficient discharge of functions and shall also follow the
guidelines, if any given by the Commission regarding the
procedure to be adopted by it for handling the complaints. .Reg.19.8
(xi)
Every order shall be a speaking order and signed by
the members conducting the proceedings. Where
the members differ on any point or points, the opinion of the majority shall be
the order of the Forum. The opinion
of the minority shall, however, be recorded and form part of the order.
(xii) The orders of the Forum shall be binding on the consumers and the
Licensee/Board. Reg.19.9
(xiii) The consumer and the Licensee/Board may obtain certified copies of the
orders, decisions, directions and reasons in support thereof given by the Forum
in respect of the complaint. Copies
of the Orders of the Forum may also be obtained by any person subject to payment
of such fees and after complying with such other terms, which the Forum may
specify. Reg.19.10
(xiv) However, any complainant aggrieved by orders of the Forum may prefer a
representation before the Ombudsman appointed/ designated by the Commission
(XV) The Forum will keep a record of consumer grievances submitted to it and
the decision thereof and make available such records for inspection of the
Commission as and when required. It
shall also submit a report on the number of grievances received, redressed and
pending, at the end of each quarter to the commission and a copy shall also be
forwarded to the distribution Licensee/Board. Reg.19.11
For any further details
PSERC Notification dated 17.8.2005 published in Punjab Govt. Gazette dated 9.9.2005 (Copy enclosed) may be referred to.
Encl:
As above.
Sd/-
Chief Engineer/Comml.
P.S.E.B.,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No.26/2006
Memo No 31998/32798
/SMI-259.
Dated: 2.6.2006
Sub: Release of temporary tubewell connections during the paddy season of
2006.
On the persistent demand of
the farmers, the matter regarding release of temporary tubewell connections for
the paddy season of 2006 has been considered and it has been decided to release
temporary tubewell connections during the paddy season of 2006 on the following
terms and conditions:-
i) The applications for temporary tubewell connections shall be accepted from 5.6.2006 to 15.6.2006 & shall be processed from 5.6.06 to
20.6.06. The connections shall be made operational from 20.6.06 onwards. All such temporary tubewell
connections shall be disconnected by 30.9.06.
ii) Temporary tubewell connections shall not be regularized as permanent subsequently.
Temporary
tubewell connection will be released only from rural feeders without resorting
to any augmentation of HT/LT lines and distribution transformer capacity. It shall be ensured that there is no overloading of distribution transformer. If
the transformer get damaged due to over loading (caused due to release of
temporary connections), concerned JE shall be held responsible. Loading upto
full capacity of distribution transformer shall be allowed as per CC.No.42/01 dated 19-6-01.
The limit
of maximum load to be applied shall be 7.5BHP and no connection for a load above
7.5BHP will be allowed.
The following
procedure shall be followed for accepting the applications for the release of
temporary tubewell connections :-
a) An application on A&A forms for getting temporary tubewell connection
will be accepted from prospective applicants alongwith non refundable processing
fee of Rs.100/-(Rupees one hundred only) per connection in the office of Addl.SE/Sr.XEN/Op.
b) Cashier from the local Sub-divison will be arranged by the ASE/Sr.XEN in
his office for accepting the processing fee.
c) Sub-Division wise list will be prepared on the same day and sent to
respective Sub-division on the next day for processing.
b) The
entry of such applications shall be made in separate service register to be maintained for release of temporary tubewell connections
during the paddy season.
c) No ACD amount shall be chargeable from such applicants.
Technical
feasibility regarding release of load will be given by Sr.Xen/Op.concerned who
will take into account the connections likely to be released against already
processed applications for new connections or extensions in load i.e. demand
notices must be taken into account before any temporary connection is released
from the same system. The voltage drop calculations of LT side must be made so
as to remain within the permissible limits of 6% on rural feeders.
Additional
SE/Sr.Xen/Op. shall personally monitor the release of temporary tubewell
connections and shall ensure that there is no bungling. He will also be responsible to ensure that feeder and pole mounted Sub-station is not
overloaded. Further it should be ensured that the list of areas where temporary
connection can be allowed is displayed at the Sub-divisional office.
If it is
technically feasible to release the applied load, the demand notice should be
issued to the applicant immediately asking him to deposit the charges as Rs. 1500/- (Rupees one thousand five hundred only) per BHP
which shall be non refundable for getting temporary tubewell connection
The
service cable length of connection shall normally be limited to 100 mtrs.
However in hardship cases the length of service cable may go upto a maximum of
110 mtrs.
The
connection shall be released from the nearest pole by providing cut-outs of
proper capacity. An identification plate indicating name of the consumer, A/C
No. and connected load etc. shall be displayed near the point of T-off to
identify the consumer. Alternatively the said particulars shall be printed on
the nearest PCC Poles.
The
applicants will have to provide their own material for release of such
connections, which will be returned to them after disconnection on 30.9.2006.
If
a temporary tubewell consumer is found to have installed a higher motor than the
sanctioned one, he shall be levied a load surcharge of Rs. 1000/- per BHP as
well as consumption charges @ Rs. 1500/- per BHP for the extra load detected
provided the total installed capacity does not exceed 7.5 BHP and feeding
transformer is capable of taking the additional load . In case any unauthorized
temporary tubewell connection is found to be running, the same shall be got
disconnected and consumer shall be dealt as per latest instructions of theft of
energy .
Distribution
Wings and Enforcement Agencies shall
carryout intensive checking to
ensure that motors installed by the consumers are strictly as per sanctioned
load .
All
temporary connections must be disconnected by 30-9-06 for which PDCO shall be
issued alongwith connection release order.
Besides
new applicants, the applicants who are awaiting tubewell connections after
submission of test reports shall also be considered eligible for release of
tubewell connections in case their turn for release of connection does not
mature before the onset of paddy season. Similarly, all applicants whose
applications for tubewell connections are pending at any stage shall also be
eligible for getting temporary tubewell connections.
The
instructions issued vide CC No.50/04 dated 29-8-04 regarding procedure for
accounting of charges deposited against release of temporary tubewell
connections shall be applicable.
Field
officers are requested to give wide publicity to this scheme through all
possible means including announcements through Public Address Systems of Gurudwaras / Mandirs etc.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No 25 /2006
Memo No. 31083/3188 / SSM-414/06-07
Dated: 2/6/2006
Sub:- Release of tubewell connection under general category.
As per present tubewell
policy, the cut off date for issue of demand notices under general category is
31.3.91.However it has been reported that under some Sub-Divisions, the tubewell
connections have been released to applicants registered upto 31.3.91 whereas in
some other areas, applicants registered during 1984-85 are still waiting for
release of connection. In order to remove this disparity , the matter has been
considered & it has been decided as under :-
I) Issue of material for release of
new AP tubewell connections will be allowed only in respect of test reports received against applications registered upto 31.3.88 in the
order of seniority based on the date of registration of the application.
II) No material shall be issued by Stores Orgn. for the release of tubewell
connections under general category against applications registered after
31.3.1988 till the back log of applications registered upto 31.3.88 is cleared
in all the zones and revised
instructions will be issued thereafter .
iii) The works already in hand for which sufficient material stand issued
before 31.5.2006 shall be completed & may not be withheld on account of
above instructions. However, where only Poles and fittings /stay set etc. have
been issued, no further material be
issued.
iv) All out effort shall be made by the field officers to clear the
applications registered upto 31.3.88 and a certificate to the effect that all the AP T/W applications registered upto 31.3.88 under general
category have been released T/W connections & no application registered upto
31.3.88 under general category is pending shall be sent by the concerned CE/DS
to CE/Commercial.
The strict compliance of
above instructions be ensured by all the field officers
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.No.
24/2006
Memo No. 30119/30919
/ SSM-249/VDS/SP
Dated: 1/6/2006
SUB:- Regularization of temporary tubewell connection released during paddy
season of 2005.
It has come to
notice that a no. of AP tubewell applicants who had got their applications
registered many years ago had applied for smaller T/W motors of 3 BHP or 5 BHP
but with the declining of water table, such applicants had taken temporary
tubewell connections of higher capacity motors. There may be some cases where temporary tubewell connections had been
taken for lesser load due to system constraints but the load applied for regular
tubewell connection is higher. The
clarifications have been sought by the field officers as to which of the load is
to be regularized.
The matter has
been considered and it has been decided that temporary tubewell connection shall
be regularized for the load released during paddy season of 2005 or load applied
for the regular tubewell connection whichever is higher. However, in cases where applied load is more than the load of temporary
tubewell connection released during the paddy season of 205, tubewell connection
corresponding to applied load will be regularized if the loading conditions
permit. However, in such cases where
loading conditions do not permit release of tubewell connection as per applied
load, the tubewell connection as per load of temporary tubewell connection shall
be regularized.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No 23 /2006
Memo No.27938/28738 /SSM-249/AP.
Dated: 26/5/2006
Sub: Voluntary Disclosure Scheme vis-à-vis compulsory regularization of
unauthorized extension in load by Agriculture Tubewell consumers.
As per feedback from the field officers, a no. of AP consumers have installed motors of higher capacity than the sanctioned
loads. On detection of excess load
of such consumers by field / Enforcement Officers, they are levied load
surcharge and are asked to remove the excess load, as per present instructions,
which they seldom remove. Thus, this excess load continues to be on the system
leading to higher losses (as AP consumption corresponding to excess load is not
accounted for while working out losses) & overloading / breakdowns.
Accordingly there has been feedback from the field officers that the
unauthorized load of AP consumers should be regularized after
recovering appropriate charges. There has been demand from the various Kissan Unions also that VDS for AP consumers on
the pattern as introduced in 2004-2005 may be introduced again.
2. The matter has been considered and it has been decided to introduce the
VDS for AP consumers under which they will be able to voluntarily disclose /
declare their excess / unauthorized load & get the same regularized after
paying requisite charges as per VDS . The scheme will remain inforce from
1.6.2006 to 30.6.2006.
3. The charges for
regularization of the excess / unauthorization load so declared under VDS
shall be Rs.1000/- per BHP as Service connection charges and Rs.200/- per BHP as
ACD,without levy of any load surcharge.
4. The scheme will close on 30.6.06 & after 30.6.2006, if the load of
any AP consumer is found more than the sanctioned load during checking by the
Operation/Enforcement officers, the excess load so detected shall be
compulsorily regularized after charging Rs.1000/- per BHP as SCC and Rs.200/-
per BHP as ACD besides Rs..1000/- per BHP as load surcharge. This scheme of
compulsory regularization shall remain inforce only upto 30.9.2006 i.e. from
1.7.2006 to 30.9.2006.
5. Salient features of the scheme shall be as under:-
(i) The regularization shall be done immediately as deemed regularization on
detection of unauthorized load or self-declaration by the consumer regarding
unauthorized load. It is emphasized that the farmers who visit the sub
divisional offices for regularization of the additional load should be attended
properly and promptly. His application regarding declaration of the additional
load be accepted and necessary entries of the additional load be made in his
passbook and ledger and the BA-16 Receipt issued for the charges recovered. The
consumer shall install the shunt capacitors of requisite capacity as per the
total load and the test report shall be arranged by SDO Incharge through JE
Incharge who should indicate total load of the motor and KVAR capacity of the
Shunt Capacitor installed. The requirement of new forms has been dispensed
with. The extra load shall be regularized after deposit of requisite charges for
extended load only and getting suitable entry made in the passbook.
(ii) Augmentation of the line and distribution transformer, wherever required
after due consideration / verification by Sr.XEN/Op. concerned shall be done by
PSEB at its cost. For the purpose of regularization of the load, the loading of
the transformers may be taken as 100% instead of the existing 80%. Secondly, in
case, with the addition of unauthorized load, the loading becomes beyond 100%,
additional transformer(s) of 25 KVA shall be installed with the approval of
concerned SE/Op. However, the regularization of unauthorized load shall not be withheld due to over
loading of distribution transformer as the unauthorized hidden load was already
on the system .
Field officers are requested to give wide publicity to this scheme and
organize mass consumer contact camps in rural areas to regularize the higher
capacity motors on the spot during the VDS period.
Sd/-
Dy.CE/Sales,
for CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.
No. 21/2006
Memo
No. 25485/26295/SMI-24 Dated:
16.5.2006
SUB:- Time limit for Grant of Connection- Clause –24 of PSEB Electricity
Supply Regulations.
President, State Consumer
Disputes Redressal Commission,
Punjab
has emphasized that PSEB's counsels should be briefed properly by the field
officers/officials about the instructions issued vide CC.No. 57/2001 dated
11.7.2001 and reiterated vide CC.No. 52/03 dt. 11.8.03 according to which there
is no time limit prescribed for release of connection. The correct facts should
be brought before the Commission so as to avoid any wrong judgement.
The above instructions as per Clause –24 of PSEB Electricity Supply
Regulation Clause No. 24 (Time limit for
grant of connection) are reiterated as under: -
"It
shall be ensured by the field officers that demand notices are issued to
applicants of various categories very carefully taking all the circumstances
into account viz-a-viz availability of funds, material, power position and
loading conditions of system etc. Once the prospective consumer complies with
the demand notice, efforts shall be made by the field officers for release of
connections as early as possible."
All the field officers/officials should
note the above instructions for strict compliance. The Board's counsels should
also be briefed properly about the above instructions emphasizing that at
present there is no time limit prescribed for issue of demand notice.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.
No. 19/2006
Memo
No. 24340/25140/SMI-259 Dated:
3.5.2006
Sub: Policy for regularization of Temporary tubewell
connection released during the paddy season of 2005.
A priority scheme for
regularization of temporary tubewell connections released during the paddy
season of 2005 was introduced vide CC No.9/06 dated 24.2.06 followed by some
clarifications/amendments vide CC No.12/06 dated 17.3.06 & CC No. 15/06
dated 10.4.06. There have been
reports from the field officers that applications for regularization of the
temporary tubewell connections against which clarifications had been sought by
them from this office had not been registered for want of clarifications.
In view of the position
explained above, the matter has been considered & it has been decided that
priority scheme for regularization of temporary tubewell connections introduced
vide CC No.9/06 dated 24.2.06 followed by CC No.12/06 dated 17.3.06 and CC
No.15/06 dated 10.4.06 shall now remain operative upto 31.5.06 i.e. eligible
applicants can now opt for regularization upto 31.5.06. Further, the date for completion of work for regularization of temporary
tubewell connections is also extended from 31.5.06 to 30.6.06.
All other applicable
terms and conditions as per CC 9/06, followed by CCNo.12/06 dated 17.3.06 &
CC No.1/06 dated 10.4.06 shall remain the same.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 18/2006
Memo No. 23039/23839
Dated : 27.4.2006
Sub: Meter Rentals/Cost of Meter & Metering equipment/ Meter security .
In continuation to this office CC No. 24/2000 dt. 7.4.2000
and CC No. 58/2000 dt. 10.8.2000.
1. Punjab State Electricity
Regulatory Commission vide their letter No. PSERC /DTJ/8/2297 dt. 18.4.2006 has
granted approval to the revised meter rentals, recoverable cost of meter in case
of damage of meter due to fault/negligence of the consumer and the rates of
meter security. The revised rates applicable w.e.f. 1.4.2006 are as under:-
METER
RENTALS (Per month) |
Sr.No. |
Description |
Existing
Rates
(Rs.) |
Revised
Rates
(Rs.) |
1 |
Single Phase Static Meter |
22 |
5.00 |
2 |
MCB for Single Phase Meter |
6 |
5.00 |
3 |
Poly Phase Meter without CT |
41 |
11.00 |
4 |
MCB for Poly Phase Meter for whole current and CT
Operated |
Poly Phase
8 Meter
TPT
22 |
9.00 |
5 |
LTCT operated Meter/TPT Meter without CTs |
Poly Phase
125 Meter
TPT 320 |
72.00 |
6 |
LT CTs (Set of 3 Nos) |
for 50/5A 57 and for
100/5A & 42 upto 400/5A |
17.00 |
7 |
HT, TPT metering equipment without CT/PT Units |
320 |
88.00 |
8 |
11 KV combined CT/PT unit (10/5A to 50/5A Cap.) |
1.6 paisa per rupee cost of
metering equipment |
467.00 |
9 |
Cubical/Chamb er for Poly phase LT CTs |
22 |
18.00 |
10 |
Single Phase Electro-mechanical meter |
11 |
11.00 |
11 |
Other LT/HT/EHT Poly Phase Meter/ metering equipment not
covered under Sr. No. 1 to 10 above |
1.6 paisa per rupee cost of
meter/metering equipment |
1.6 paisa per rupee cost of
meter/metering equipment |
Note: (i) Since PSEB has stopped the purchase of
electro-mechanical meters as such the rates of meter rentals as per CC 24/2000
shall continue to be levied where electromechanical meters are still installed.
(ii) These meter
rentals would be applicable to all the existing/new consumers.
2. RECOVERABLE COST OF METERS: The recoverable cost of meters in case of damage of
meter due to fault/negligence of the consumers is as under:-
Sr.No. |
Description |
Existing
Rates
(Rs.) |
Revised
Rates (Rs.) |
1 |
Single Phase Static Meter |
1370 |
320 |
2 |
Poly Phase Meter without CT |
2570 |
670 |
3 |
LTCT operated Meter without CTs
LT TPT Meter |
7840.
13625 |
4480 |
4 |
LT CTs (Set of 3 Nos)
for 50/5A and
for 100/5A and upto 400/5A |
1580
600 |
1080 |
5 |
HT, TPT metering equipment wihtout CT/PT Units |
15625 |
5490 |
6 |
11 KV combined CT/PT unit
(10/5A to 50/5A Cap.) |
40470 |
29180 |
7 |
Single Phase Electro-mechanical meter
Full damage Repairable |
695
200 |
320
200 |
Note: (i) Where electronic meters are damaged due to fault or negligence of
consumers full cost of meter/metering equipment should be charged as these
meters are not repairable and have to be scrapped/disposed off.
3. METER SECURITY: The rates of security for various types of
meters/metering equipments are as under:-
Sr.No. |
Description |
Existing
Rates
(Rs.) |
Revised
Rates
(Rs.) |
1 |
Single Phase Static Meter |
600 |
270 |
2 |
MCB for Single Phase Meter |
- |
270 |
3 |
Poly Phase Meter (whole current) |
1500 |
550 |
4 |
MCB for Poly phase meter |
- |
400 |
5 |
3 Phase meter/ TPT.Meter without CTs |
4000
15000 |
4200 |
6 |
LT CTs (Set of 3 Nos)
for 50/5A
for 100/5A and upto 400/5A |
800
400 |
1050 |
7 |
HT, TPT meter without CT/PT Units |
10000 |
5250 |
8 |
11 KV combined CT/PT unit (10/5A to 50/5A Cap.) |
25000 |
28500 |
The revised rates are applicable w.e.f. 1.4.2006. Operation
offices and Billing organization should keep a note of the revised rates and
bills to be issued henceforth should contain the revised rates. Wherever these
charges have been recovered as per pre-revised
rates, necessary refund/adjustment shall be made in the subsequent bills. Field
Officers are requested to give wide publicity to the above instructions.
Sd/
Director/Sales-II
For
CE/Commercial,
PSEB
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.
No. 16/2006
Memo
No. 19333/20133/SSM-451-A/Vol.II Dated:
17.4.2006
Sub: One Time
Settlement offer for all categories of permanently disconnected defaulting
consumers.
As
per instructions issued vide CC No.50/2005 dated 28.07.2005, the One Time
Settlement (OTS) package introduced vide CC No. 42/2002 dated 12.08.2002 was
available upto 31.12.2005 for reconnection of various categories of consumers,
whose connections were disconnected temporarily/ permanently upto 31.12.2004.
In view of the encouraging response of
the consumers, the matter has been considered and it has been decided to extend
the One Time Settlement package upto 30.9.2006 for revival of sick industry and
other categories of consumers. With
this extension, the consumers whose connections were disconnected temporarily
/permanently upto 31.3.2005 can opt for reconnection upto the validity of the
scheme i.e. 30.9.2006.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
15/2006
Memo No.
18308/19108/SMI-259 Dated: 10.4.2006
Sub: Regularization of temporary tubewell
connection releaseed during paddy season of 2005.
A priority scheme for regularization of temporary tubewell connections
released during the paddy season 2005 was introduced vide CC No. 9/06 dated
24.2.2006 and was operative upto 15.3.2006. However vide CC No. 12/06 dated
17.3.2006 ,the scheme was extended upto 31.3.2006.
2. Based on the representations received from the individual
applicants, a no. of clarifications have been sought by the field officers. The
matter has dbeen reviewed in the light of various clarification sought by field
officers and it has been decided as under:-
i) As per Condition No. (ix)of CC No.9/06 dated 24.2.2006, the field
officers were required to ensure that the work for the regularization of
temporary tubewell connection is completed by 31.3.2006 which has now been
extended to 31.5.2006.
ii) The application for regularization of temporary T/W
connection,from an applicant in whose case application for regular T/W
connection stand registered on or before 31.5.2005 in the name of this first
blood relation (i.e father/mother/brother/sister/daughter or daughter
–in-law/son or son-in-law) or legal heir, be also considered for
regularization.
iii) As per Condition No.(vii)of CC No. 9/06 dated 24.2.2006 ,the
length of 3.5 core LT XLPE cable
shall not be more than 10 mtrs. However,where total length of cable required for
T/W connection is only upto 20 mtrs,it may not be advisable/economical to erect
the line on poles & in such cases the connection be released through 3.5
Core LT XLPE cable
only after ensuring that the length of service cable does not exceed 20 mtrs in
any case.
iv) In case the regularization of temporary T/W connection is sought
by an applicant at a new bore/site due to non availability of water at the
bore/site where temporary tubewell connection had been obtained during the paddy
season of year 2005, the regularization in such a case be allowed subject to the
condition that the new bore/site is within the same Khewat/Killa and total
length of the LT line is not more than 110 mtrs. Further, the applicant shall be
asked to furnish an undertaking on stamp paper indicating reasons for change of
site /bore and if at a later stage he is found misusing his previous bore then
his connection will be liable to disconnected.
All
other applicable terms and conditions as per CC No.9/06 dated 24.2.2006 followed
by CC No.12/06 dated 17.3.2006 shall remain the same.
Dy.Chief Engineer/Sales
For
Chief Engineer Comml.
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC: 14/06
Memo No. 17291/18091/SSM -459 Dated:
31/3/2006
Subject: Grant of power connection to wood-based industries.
Secretary to Government Punjab, Department of Industries & Commerce
Punjab has forwarded a copy of the Hon'ble Supreme Court orders dated 30.10.2002
passed in Writ Petition (Civil) 202 of 1995 relating to Saw Mills / Veneer /
Plywood Industries in the State and it has been requested that in future no
power connection may be granted to the wood based industries unless they have
been granted SSI registration by the concerned General Manager / District
Industries Centre.
The matter has been considered and it has been decided that henceforth
power connection shall not be granted to any wood based industries unless it has
been granted SSI registration by the concerned General Manager / District
Industries Centre. These instructions shall come into force with immediate
effect.
Dy.C.E/Sales
For
C.E./Comml.,
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC:
13/2006
Memo
No. 15164/15964/SSM-414/ L Dated: 17.3.06
Subject: Tubewell Policy-Release of Tubewell Connection on H.T.
Instructions were issued vide CC No.68/05 dt. 1.12.05 that new AP
tubewell connections shall continue to be released on LT upto 31.3.06.
The matter has been reviewed again and keeping in view the supply
position regarding availability of 6.3/10/16 KVA distribution transformers, it has been decided that new A.P tubewell connections on L.T supply shall, now, continue to be
released on LT upto 30.9.2006.
All other terms & conditions as per CC-38/05 dated 6.6.05 &
47/05 dated 20.7.05 shall remain applicable.
Dy.C.E/Sales
For
C.E./Comml.,
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC:
12/2006
Memo No. 16112/16912/ SMI/259 Dated: 17.3.2006
Subject: Regularization of Temporary Tubewell Connection released during Paddy
Season of 2005.
. A priority scheme for regularization of temporary tubewell connection
released during the paddy season 2005-06 was introduced vide CC-9/06 dated 24.2.06. This priority was admissible upto the
release of connection and was inforce upto 15.3.2006 i.e. eligible applicant
could opt for regularization upto 15.3.2006. There is a feedback from the
field officers that there could be many cases where the consent of the
consumer could not reach by the cut off date of giving option i.e. by
15.3.2006.
The matter has been reviewed and it has been decided that the cut-off
date for the regularization of temporary tubwell connection introduced vide
CC.No. 9/06 dated 24.2.06 shall now be operative upto 31.3.2006 i.e. the
eligible applicant can now opt for regularization upto 31.3.2006.
All other applicable terms & conditions as per CC-9/06 dated
24.2.06 and CC25/05 dated 25.4.05 shall remain the same.
Dy.C.E/Sales
For C.E/Comml.,
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 10/2006
Memo No.12106/12906/Free Supply /AP
Dated : 1-3-2006
Sub: Free Electricity to
Agricultural Tube well consumers.
It has been decided by Govt. of Punjab to give FREE ELECTRICITY w.e.f.
1.9.2005 onward, to all categories of Agricultural Tube Wells such as Tube
wells covered under Flat Rate/ Metered Supply category, Agricultural Tube
Wells released under SP category, tube well connections released to farmers of
Kandi Area, PAU Ludhiana, PSTC/IB, lift Irrigation, other connections released
under SP/MS category and under TCA (Technical Co-op. Assistance). It has also
been decided to give free supply to only those tubewell consumers who are not
defaulters of energy/flat rate charges for the period pertaining upto 31.8.05.
Defaulters as on 31.8.05 shall continue to receive bills wherever computerized
bills have been introduced. Where computerization has not started, hand
written bills maybe sent to all defaulting tube well consumers who have not
paid the bills for the period upto 31.8.05 However, once such defaulting
consumer come forward anytime w.e.f. 1.9.05 to pay the defaulting amount
relating to the period upto 31.8.05, then in that case the consumption charges
for the period starting from 1.9.05 shall not be charged. Once they pay
defaulting amount upto 31.8.05, no bill shall be sent to the consumer.
For implementing the above decision, an entry under the signatures of
AE/AEE (op.) in the consumer ledger shall be made in Red Ink in respect of
defaulting consumer as on 31.8.05.
As & when defaulting amount is paid, this entry shall be struck off and no
further bills shall be raised. Secondly the Pass books already issued/ to be
issued to the Agricultural Consumers shall be stamped with a free supply entry
in green ink and signed by the AE/AEE incharge.
Thirdly the tubewell ledger containing details of AP consumers may be marked
as free supply ledger. All new connections/extension shall be entered in this
free supply ledger (maintained in CBC for computerized bills or sub division
for manual pass book system) as & when these are released. Red ink entry
in respect of defaulting consumers be also made in free supply ledger.
Similarly as & when a motor of higher capacity is detected by Enf.
or operation staff and/or extension in load is declared by the consumer under
VDS, an entry of the correct/increased size/capacity of the motor should be
entered in the pass book immediately and a corresponding entry in the consumer
ledger should be made without any delay.
The existing ledgers for tube well consumers should continue to be
maintained as here-to-fore and flat rate charges/metered consumption charges
should be entered every month/bimonthly as per the existing billing cycle.
Computerized ledgers should also continue to be prepared as here-to-fore. However there is no necessity to generate computerized
bills except in case of defaulting tube well consumers. Wherever metering is
being done, reading of meters should continue as here-to-fore and consumption
charges entered in ledgers. Field officers are requested to serve notices to
defaulters as on 31.8.05 that they
will get the facility of free supply only if they clear their pending dues
pertaining to the period upto 31.8.05.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC: 09/2006
Memo No 11948/12748 / SMI-259 Dated: 24.2.2006
Subject: Regularization of Temporary Tubewell Connection released during Paddy
Season of 2005.
. Vide CC-No.25/05 dated 25.4.05, temporary tubewell
connections were allowed to be released during the paddy season of 2005. These
temporary tubewell connections were made operational from 10.6.05 onwards and
were disconnected by 30.9.05. There are large number of farmers who have
applied for the release of regular tubewell connection from PSEB but are still
awaiting for their turn for release of the tubewell connection as per
seniority.
The matter was considered & keeping in view the fact that temporary
tubewell connection during the paddy season of 2005 were released considering
the existing loading condition of the distribution transformers & the
system is capable of taking this load, it has been decided to regularise the
temporary tubewell connections released during the paddy season of 2005 of
only those applicants who have otherwise registered their applications with
PSEB for the release of regular tubewell connection under general category or
any priority category upto 31.5.2005 subject to the following terms &
conditions:
(i) Only those applicants who have otherwise registered their applications
with PSEB for release of regular T/W connection under general category or any
priority category up to 31.5.05 and were released temporary T/W connections
during the paddy season of 2005 will be considered for regularization under
the priority scheme.
(ii) This shall be a priority scheme admissible upto the release of
connection and shall remain inforce upto 15.3.06 i.e. the eligible applicant
can opt for regularization upto15.3.06. The priority for regularization of
temporary T/W connection shall be allowed by concerned Sr.Xen/Addl.SE Op.
under intimation to concerned SE/Dy.CE/DS.
(iii) Requests received for regularization of the temporary tubewell
connections released during the paddy season 2005 shall be processed on the
basis of the seniority of the applications registered by such applicants for
regular T/W connections maintained at the sub-divisional level. The Tubewell
connection against regular application of such applicant will be considered as
released.
(iv) As per SR No. 13.5.5. for claiming priority under this scheme, applicant will be required to furnish an
undertaking on a non judicial stamp paper worth Rs.15/- that in case of mis-representation
or misuse of priority by sale, lease or transfer of connection or change of
name within 5 years from the date of release of connection , his connection
shall be disconnected. A note to
this effect shall be made on agreement and undertaking shall be tagged to the A&A form to be kept in safe custody as per SR No.32.
(v) The applicant shall be required to deposit Rs.5000/- per BHP as
seecial priority charges through demand notice in addition to Rs. 200/- per
BHP as ACD.
(vi) The cost of material required for regularization of the
temporary T/W connections including labour charges shall be borne by the
applicant for which estimate shall
be framed by the field office. However, no supervision charges shall
be levied.
(vii) The length of LT line including service cable shall not be more
than 110 mtrs, in any case, for individual connection and the span length of
LT line shall be restricted to 50 mtrs. The 3.5 core LT XLPE cable shall not
be of more than 10 mtrs. length.
(viii)
The
overall total length of LT line/service cable route length shall not be more
than 500 mtr. from the common pole as per existing instructions. No
augmentation of LT/HT line shall be permissible under this scheme. While
allowing release of connection, it shall be ensured by Sr.Xen/ Addl. SE/DS
that loading of distribution transformer and voltage regulation of feeding
LT/HT line are within permissible limits.
(ix) In the first instance connection shall be released by laying LT Cable on PCC Poles (if required).
The cable will be provided by the consumer (may be the cable used earlier for
release of Temporary T/W connection). It shall be ensured by the field
officers that the work for regularization of temporary T/W connection is
completed by 31.3.06 (present cut off date for release of new AP T/W connection at LT supply). The
cable shall be subsequently replaced with overhead conductor before 30.06.06 positively( required as per provision in individual
estimate).
(x) No extension in load shall be allowed to such regularized T/W
connections upto a period of 3 years from the date of release of connection.
(xi) In case any deviations are found at a later stage, Sr.Xen/ Addl.SE/Op shall be personally responsible and strict disciplinary
action shall be taken against him.
(xii) An applicant, who gets his temporary tubewell connection
released during the paddy season of 2005 regularized, will not be eligible for
release of temporary tubewell connection during the next year.
All other applicable terms and conditions as per CC 25/05 dated
25.4.2005 shall remain the same.
Dy.C.E/Sales
For
C.E./Comml.,
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC:
8/2006
Memo No. 10629/11429 / SMI/102/1 Dated: 17.2.2006
Subject: Shifting of Poles/ Lines under Deposit estimate/improvement of LD system.
There has been reports from the field that while shifting poles/lines
from the plot/land of a person against a Deposit estimate/improvement of LD
system, the interest of neighbouring plot/land holders are not kept in view by
the field officers which leads to avoidable complaints and litigation. It has
been reported that in a no. of cases the poles/lines while shifting from the
plot/land of one person are often installed / erected in a plot/land of
neighbouring person which is not fair. Justice demands that with such shifting
of pole/lines the interests of neighbourers should not suffer.
In
view of above, it should be ensured by field officers that shifting of
poles/lines against a deposit estimate/improvement of LD system is carried
out, after thoroughly ascertaining technical feasibility and also keeping in
view ultimate planning of the area /interest of neighbouring persons. The
deposit estimates should be prepared accordingly & if need be concurrence
/approval of Panchayat/Local Body should be obtained before such shifting is
permited.
Dy.C.E/Sales
For
C.E./Comml.,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC_7/2006__
Memo
No.9103/9903 Dated
: 8.2.06
Sub:- Extension in load and checking of connection
by the Enforcement/Op. Organization during the intervening period after the
issuance of Demand Notice and
before/after submission of Test Report by the consumer.
1. (a) It has come to the notice of this office that
Enforcement/Op. Organization are checking connections of the consumers who have
applied for extension in load and Demand Notice stand issued but submission of
the test report is pending for release of extension in load. During this
intervening period the consumer is in a process to install his load and
machinery and sometimes also test the machinery by connecting to PSEB supply.
During
checking by the Enforcement/Op. such
loads which are yet to be released are being declared un-authorized and heavy
penalty is levied and a dispute
arises between the PSEB and the consumer. To settle the dispute consumer has to
file his case before Dispute Channel after deposit of 33% of the disputed amount
and thus is subjected to avoidable harassment. In a number of cases charges
billed are found to be not leviable.
(b) In some
cases some premises have been checked where test reports has been submitted by
the consumers but release of connection by the Board is awaited.
2. (a) To settle such cases speedily & to avoid inconvenience/harassment to
the consumer it has been decided as under:.
(i) Such consumers who feel that injustice has been done
to them, can make a representation to CE/DS concerned.
(ii) If CE/DS is satisfied with the version of the
consumer after getting the required feed back from Field Officers, he will send
the representation of the consumer along with his recommendation, without any
deposit money to CE/Commercial for putting up to the Chairman for
consideration/Decision.
(a) It has also been decided that if the consumer has
submitted the test report then it shall not be treated as a case of unauthorized
connection.
The
Sales Regulation Clause 28.8 stands amended to the above extent.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC: 6/2006
Memo
No. 8043/8843/ SMI/102/1 Dated: 6.2.2006
Sub: Installation of meter cup boards (MCBs).
As
per Sales Regulation-79.1, meter/metering equipment is to be installed in a
MCB (Meter cupboard) of the design approved by the Board. Further, as per SR
79.1.1 in case of existing connections where MCB has not been provided or if
provided the same is not of the design approved by the Board,a 30 days
registered notice is required to be issued by the field officers to all such
consumers for providing MCB of the design approved by the Board otherwise, the
Board shall provide the same at consumer's cost and will debit rentals as per
prescribed rates through energy bills.
The matter has been reconsidered and it has been decided as under:-
1. As
per existing instructions (SR 79.1)all the new connections shall continue to be released by
installing electronic meters in MCBs of the design approved by the Board.
2. In theft prone areas, the meters shall be installed in
the Meter Pillar Boxes of the design approved by the Board.
3. In case of existing connections where electro
mechanical meters stand installed without MCBs, MCBs shall not be installed.
4. In case of existing connections where electro
mechanical meters have been or are being replaced with electronic meters
without installation MCBs due to shortage of MCBs, the MCBs shall be installed
in all such cases.
SR.No.
79.1 and 79.1.1 may be considered as amended to the above extent.
Strict
compliance of the above instrucitons may be ensured.
Director/Sales
For C.E./Comml.,
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
CC No. 5
dated 3-1-2006
Memo No.
6027/6827/DB-53 dated 31-1-2006.
SUBJECT: Withdrawal of Advance Deposit Scheme of Electricity Bills by consumers
and payment
of incentive thereof.
Advance Deposit Scheme was introduced vide this office CC No. 28 dated
25-4-03 for DS, NRS, SP and AP consumers who opt for it. The Board was constrained to withdraw the scheme because of poor
response even though wide publicity was given in news papers and interaction
with consumers by holding meetings at various levels. The Board has incurred loss.
In view of above facts the Board has decided to withdraw Advance
Deposit Scheme for General, SP and AP consumers w.e.f. 31-1-06. The scheme will however be continued for only whose General & SP
consumers who had already deposited the money under this scheme till whole of
the advance is adjusted against their bills. The payment of additional 2 paise per bill for Advance Deposit Scheme
to M/s DOEACC will be stopped w.e.f. 31-1-06 and thereafter for the left out
consumers the calculation for incentive to be given shall be carried out by
respective Operation Sub Divisions. For
AP consumers, the amount outstanding as on 31-3-05 will be refunded.
Sd/-
Dy. CE/Billing
For CE/Commercial,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.
No. 4/2006
Memo
No. 6932/7732/SSM-594 Dated:
30.1.2006
Sub:- Parallel Operation Charges.
Ref:- CC.No.26/02 read with CC.No.60/02.
While considering the issue regarding recovery of parallel operation
charges from Captive Power Plant owners, the PSERC vide para 8.13 of Tariff
Order for 2005-06 decided as under:-
“ The Commission therefore
decides that till the study is complete the parallel operation charges being
levied on Captive Power Plant owners shall continue to be levied at the
prevalent rates. These parallel operation charges shall be leviable on all
Captive Power Plants which run in parallel/synchronism with grid of the Board,
irrespective of the fact whether Captive Power Plant owners are consumers of the
Board or not. The Commission further decides that adequate measures be taken by
the Board to ensure that no Captive Power Plant owner is allowed to run the
plant in parallel with the Board’s system without prior permission and getting
the adequacy of the protection system checked from the Board.”
2. In partial supersession of the instructions contained in Commercial
Circulars 26/02, 60/02 and Sales Regulations No.170, it has now been decided
that:-
(i) the competent authority while according approval to the proposal of the
Captive Plant/Co-generation plant owners to run the plant in parallel with the
grid/Board’s system shall get the
adequacy of protection system and protection co-ordination vetted from the
Sub-station Design Directorate. Further Captive Power Plant/Co-generation Plant
owners before actually running the plant in synchronization shall also get the
approval of the concerned officer of Protection Wing regarding provision of
adequate protection system.
(ii) it shall be ensured by the Senior Xen/Operation concerned that no such
plant is allowed to run in parallel with the Board’s system/grid without
approval of the competent authority as per (i) above.
(iii) all the Co-generation Plant owners/Captive Plant owners, irrespective of
the fact whether they are Board’s consumers or not, running the plant in
parallel with the grid/Board’s system as mentioned above, shall be required to
pay parallel operation charges.
(iv) the plant owners who intend/actually operate the plant to feed their load
on stand-alone basis shall not be required to pay parallel operation charges.
3. These instructions shall be effective from April 1,2005.
Sd/-
Chief Engineer
Comml,
PSEB,
Patiala
-----------------------------------------------------------------------------------------------------------------------------------------------------
C.C.
No. 3/2006
Memo
No. 4224/5024/SSM-580 Dated:
17.1.2006
Sub: Setting up of Grievance Cell in the Head Office
Patiala
.
In view of Joint Secretary/Personnel Office Order No. 9460/Cadre-1 dated 03.11.2005 ,the instructions issued vide
CC.No.56/2004 dated 4.11.2004 are amended to the extent detailed hereunder :-
“The concerned SE/DS shall only be the convener of
the Grievance Cell
instead of Member/Convener. “
Further Para (V) of the functional instructions for the working of
Grievance Cell is amended to read as under :-
“The final decision of Grievance Cell shall be conveyed by the convener to CE/DS through fax and to the
consumer, if he has the fax facility”.
All other terms & conditions of CC No. 56/04 shall remain unchanged.
Sd/-
Dy.CE/Sales
For
CE/Commercial
PSEB,
Patiala
----------------------------------------------------------------------------------------------------------------------------------------------------- CC_2/2006__
Memo
No.3271/4071/Inds. MSR
Dated
: 16.1.2005
Sub:- Appeal against the reviewed assessment.
If a consumer is not satisfied with the decision of Dispute Settlement
Committee/Dispute Settlement Authority, he can file an appeal against the
reviewed assessment. As per Sales Regulation Clause 144.2, the consumer filing
the appeal against the reviewed assessment is required to deposit 50% of the
balance disputed amount in addition to the 33% of the amount already deposited
by him.
It
has been decided that in hardship/deserving cases, amount to be got deposited
can be reduced to less than 50% of
balance disputed amount for filling appeal with approval of Chairman, PSEB.
SR
144.2 may be considered as amended to this extent.
Sd/
Director/Sales-II,
PSEB,
Patiala
.
-----------------------------------------------------------------------------------------------------------------------------------------------------
C:
1/2006
Memo
No. 2357/3157 / SSM-327 Dated: 16.1.2006
Sub: Commercial Circulars issued during the year 2005.
In total 72 NO. Commercial
Circulars have been issued during the year 2005 with No. from 1 to 72 .
Subjectwise list of circulars is enclosed for the convenience &
information of field offices
Dy.C.E/Sales
For C.E./Comml.,
PSEB,
Patiala
Subjectwise
List of Commercial Circulars issued
during the year 2005
Sr.No. |
|
No.
of Circular |
1. |
Release
of Connections |
|
a) |
Industrial |
18/05 |
b) |
Tubewells |
5/05,9/05,10/05,13/05,27/05,
32/0538/05,41/05,47/05,68/05,69/05
|
2. |
VDS |
|
a) |
DS/NRS |
7/05,45/05,63/05 |
b) |
SPp |
15/05 |
c) |
SP/MS Green Category |
21/05,43/05 |
d) |
AP |
22/05,44/05, 46/05 |
3. |
Temporary
tubewell connections |
25/05,62/05 |
4. (a) |
Tariff
& Billing |
|
i) |
Revision of Tariff w.e.f. 1.10.2004 –Amendment
undernote of CC.57/2004 dt.19.12.04 at Sr.No.10 regarding Agricultural pumpsets. |
2/05 |
ii) |
Charging of MMC on AP metered consumers |
28/05 |
iii) |
Bimonthly billing of AP consumers |
35/05 |
iv) |
Seasonal industries—Extension in seasonal period
billing |
36/05 |
v) |
Extension in seasonal period to Rice Shellers |
40/05 |
vi) |
Revision of tariff w.e.f. 1.4.2005 |
42/05, 57/05 |
vii) |
Power factor surcharge instead of capacitor
surcharge in case of MS consumers having load in the range of 21 KW to 100
KW |
56/05 |
viii) |
Raising of Min PF from 0.88 to 0.90 (Lagging) for LS
& Rly. traction consumers. |
65/05 |
ix) |
Arrear Bill to consumers |
70/05 |
4. (b) |
Excise
duty |
|
i) |
Exemption from the payment of Electricity Duty
mentioning period of exempt in electricity bill. |
12/05 |
ii) |
Levy of Electricity duty |
20/05,52/05,58/05 |
5. |
Sales
Regulations |
|
i) |
SR.No.167-Release of additional power connection to
install telecom equipment and towers antennas on ground floor |
11/05 |
ii) |
SR.39.9-New connection/Reconnection of permanently
disconnected consumers –Industrial premises purchased through auction or
otherwise revival of industry. |
31/05,51/05 |
iii) |
SR.28.8.1- Verification of extension in load |
54/05 |
iv) |
SR.14.1.6- Regarding installation of 3 phase power
socket by NRS /Industrial consumers |
59/05 |
v) |
SR.123.12-To write off irrecoverable arrears of the
cost of electric energy meter rent & service & general charges due
from consumers – Defaulting amount |
66/05 |
vi) |
SR 45.3.1 -
Regarding release of electricity connection in respect of cluster of
houses existing beyond
500 m
. of village Phirni . |
72/05 |
6. |
Miscellaneous |
|
i) |
Commercial
Circulars issued during the year 2004 |
1/05 |
ii) |
Installation of Electro-mechanical meters of
Agriculatural pump sets for the release of new connection. |
3/05 |
iii) |
Constitution of DSA & other DSCs of Board |
4/05, 29/05,39/05 |
iv) |
Computation of connected load of DS consumers |
6/05 |
v) |
Providing of power connectiosn to software Units on
priority |
8/05 |
vi) |
Shifting of tubewell connections |
14/05 |
vii) |
OTS package |
16/05,50/05 |
viii) |
Splitting
of AP connections running on rural/Urban /City Feeders due to genuine
family partition |
17/05,37/05 |
ix) |
Empanelment of Firms for private sale of meters to
consumers of PSEB |
19/05,23/05,33/05 |
x) |
Powers of Authorized officers of the Board to enter
the consumer premises for checking inspection –section-135(2) of the
Electric Act,2003 |
24/05,60/05 |
xi) |
LILO Arrangement for allowing extension in
load/contract demand with conversion of supply voltage from 11 KV to 66 KV
for existing 11 KV consumers. |
26/05,34/05 |
xii) |
Installation of Pvt. 11KV Pilfer resistant (Dry
type) CT/PT Units. |
30/05,48/05,67/05 |
xiii) |
Check the accuracy of replaced Energy meters in ME
Labs |
49/05,64/05 |
xiv) |
Hiring of PSEB poles for Cable TV Network |
53/05 |
xv) |
To write off irrecoverable arrears of the cost of
electric energy meter rent & service & general charges due from
consumers – Defaulting amount |
55/05 |
xvi) |
Payment/Recovery of interest on disputed amount |
61/05 |
xvii) |
Checking accuracy in M.E. Labs of oil filled 11KV
CT/PT Units replaced with pilferage resistant dry type 11KV CT/PT Units at
par with electromechanical meters (Single/three phase) being replaced with
electronic meters. |
71/05 |
Director/Sales
For C.E./Comml.,
PSEB,
Patiala
|