MUKERIAN HYDEL PROJECT, STAGE-I (207 MW)
 |
Mukerian Hydel Project is one of the main Hydro Electric Projects in the Northern Region situated in the Hoshiarpur District of Punjab. The Mukerian Hydel Project is run of the river project, constructed at Mukerian Hydel Channel emanating from Shah-Nehar Barrage constructed down stream of Pong Dam on River Beas . The Barrage has 52 gates and a small artificial lake of holding capacity 3404 acres feet to feed the Mukerian Hydel Channel. Mukerian Hydel Channel is 37 Km .long and lined with Cement Concrete and having maximum water carrying capacity of 11500 cusecs. The Mukerian Hydel Project comprises of 4 No. Power Houses. Power House No. 1 & 2 have 6 Nos (3 at each Power House). Machines of 15 MW capacity each whereas Power House No.III & IV have 6 No. (3 at each Power House) machines of 19.5 MW capacity each. The total generating capacity is 207 MW of all the 12 No. Machines.The Power Houses are situated at different reduced distances (RD's) of the channel and located as mentioned below:-
Description |
PH-I |
PH-2 |
PH-3 |
PH-4 |
Capacity |
45MW |
45MW |
58.5MW |
58.5MW |
R.D. |
6365Mtrs. |
16004 Mtrs. |
18879 Mtrs. |
27404Mtrs |
Location |
Talwara |
Hazipur |
Ralli |
Uchi-Bassi |
Salient features of the Mukerian Hydel Project are given as under:-
| Sr. No. |
Description of the generating units |
PH No.1&2 |
PH No.3&4 |
1 |
Rating of each units |
15 MW |
19.5 MW |
2 |
No. of Units at each PH. |
3 No. |
3 No. |
3 |
Manufacturer |
BHEL Bhopal |
BHEL Haridwar. |
4 |
Turbine Output |
21000HP |
27300HP |
5 |
Max.Net Head. |
17.5 Mrs. |
22.5Mtrs. |
6 |
Min.Net Head |
16.5 Mtrs. |
21.95Mtrs. |
7 |
Rated Net Head |
16.8 Mtrs. |
21.95 Mtrs. |
8 |
Discharge required per M/c for max. generation. |
3708 cusec |
3701 cusec. |
9 |
Type of Turbine |
KAPLAN |
KAPLAN |
10 |
No. of blades. |
6 |
6 |
11 |
Dia. of runner |
3962mm |
3650mm |
12 |
Generator voltage |
11000 Volts |
11000 Volts. |
13 |
Type of generator |
Vertical, salient pole Umbrella type. |
Vertical salient pole Umbrella type. |
14 |
Normal speed |
150 RPM |
166.7 RPM. |
15 |
Direction of rotation |
Clockwise |
Clockwise |
DETIAL OF STEP-UP TRANSFORMERS |
No. of Transformer |
Voltage Ratio in use. |
Different capacity in use.(MVA) |
No(s) in each capacity size. |
Aggregate capacity (MVA) |
|
3
3
3
3
2 |
11/132KV
11/132KV
11/132KV
11/132KV
132/66KV |
16.667
16.667
25
25
50 |
3
3
3
3
2 |
50.001
50.001
75
75
100 |
|
Total |
300.002MVA |
|
The dates of commissioning Unit wise are as under: -
| Name of PH Unit No. |
Date of Commissioning |
Date of synchronization |
Date of commercial operation |
MPH-I
Unit-I
Unit-II
Unit-III |
02.10.1983
14.10.1983
26.11.1983 |
02.10.1983
14.10.1983
26.11.1983 |
02.10.1983
14.10.1983
26.11.1983 |
MPH-II
Unit-IV
Unit-V
Unit-VI |
05.05.1988
03.06.1988
28.02.1989 |
18.05.1988
03.06.1988
28.02.1989 |
18.05.1988
03.06.1988
28.02.1989 |
MPH-III
Unit/VII
Unit-VIII
Unit-IX |
11.11.1988
26.01.1989
10.03.1989 |
29.03.1989
22.03.1989
22.03.1989 |
29.03.1989
22.03.1989
22.03.1989 |
MPH-IV
Unit-X
Unit-XI
Unit-XII |
25.12.1988
10.03.1989
01.04.1989 |
22.03.1989
22.03.1989
25.05.1989 |
22.03.1989
22.03.1989
25.05.1989 |
The generating Units at each Power House can be put in service with minimum flow of 1600 cusec. The Mukerian Hydel Project generates electrical energy at 11 KV and after stepping up to 132 KV, the same is transmitted to Grid system at 132 KV. Power House No. I, is connected with Power House No.II and Power House No.II with PH No. III and PH No. III with PH-IV through 132 KV double circuit lines carried on towers. There are four 132 KV circuit lines for evacuation of electric energy generated, two numbers at PH-II to Jallandhar (through 132 KV Bhogpur and 132 KV Tanda circuits) and other two at PH-IV through 132 KV Sri-Hargobindpur Circuit I&II.
GENERATION ACHEIVEMENTS (In MUs):
| Year |
Actual Generation (In MUs) |
|
|
MHP-I |
MHP-II |
MHP-III |
MHP-IV |
Total Gen. (In MUs) |
|
1988-89 |
222.69 |
3.35 |
- |
- |
226.04 |
|
1989-90 |
277.37 |
202.45 |
330.81 |
326.69 |
1137.32 |
|
1990-91 |
299.24 |
244.21 |
313.61 |
311.45 |
1168.51 |
|
1991-92 |
265.51 |
243.45 |
317.64 |
313.26 |
1139.86 |
|
1992-93 |
245.17 |
234.36 |
307.02 |
305.88 |
1092.43 |
|
1993-94 |
253.53 |
248.26 |
318.76 |
314.25 |
1134.80 |
|
1994-95 |
284.24 |
293.26 |
377.03 |
375..85 |
1330.38 |
|
1995-96 |
314.45 |
309.63 |
322.18 |
398.53 |
1344.79 |
|
1996-97 |
277.69 |
285.01 |
348.16 |
363.98 |
1274.84 |
|
1997-98 |
287.29 |
297.08 |
377.25 |
377.85 |
1339.47 |
|
1998-99 |
326.23 |
337.15 |
435.03 |
430.03 |
1528.44 |
|
1999-2000 |
331.05 |
341.16 |
435.51 |
439.10 |
1546.82 |
|
2000-01 |
266.16 |
270.38 |
351.41 |
332.92 |
1220.87 |
|
2001-02 |
255.32 |
257.12 |
331.44 |
322.70 |
1166.58 |
|
2002-03 |
178.35 |
171.86 |
224.96 |
220.34 |
795.51 |
|
2003-04 |
226.42 |
224.83 |
290.59 |
287.39 |
1029.23 |
|
2004-05 |
191.30 |
177.44 |
225.19 |
227.68 |
811.62 |
|
2005-06 |
272.36 |
251.39 |
357.14 |
357.36 |
1238.25 |
|
2006-07 |
260.644 |
226.236 |
344.850 |
339.005 |
1170.735 |
|
2007-08 |
292.72 |
295.97 |
390.16 |
383.05 |
1361.90 |
|
2008-09 |
250.21 |
250.62 |
322.74 |
308.29 |
1131.861 |
|
2009-10 |
195.89 |
192.74 |
249.80 |
247.66 |
885.94 |
|
2010-11 |
233.54 |
230.61 |
303.73 |
30.185 |
1069.73 |
|
NOTE:- The Mukerian Hydel Project has achieved the record generation of 1546.82 MU's in the year 1999- 2000 since its commissioning, which was the milestone in the history of Mukerian Hydel Project |